CheckbookBudget line

What has the City spent on High Voltage Conversion Program?

$29.8M across 2,167 payments, July 17, 2017 to June 16, 2026 — 1,194 purchase orders and 17 vendors, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: HIGH VOLTAGE CONVERSION PROGRAM

Spans more than one contract

This budget line has run for 9 fiscal years across 1,194 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$29.8MTotal spent
1,194Purchase orders
17Vendors
37%Largest vendor's share

Spending by fiscal year

FY2017-18
$1.7M
FY2018-19
$2.9M
FY2019-20
$4.9M
FY2020-21
$4.1M
FY2021-22
$7.8M
FY2022-23
$3.2M
FY2023-24
$2.7M
FY2024-25
$1.4M
FY2025-26
$1.1M

Who was paid

KDC Inc$11.0M

114 payments

38 payments

16 payments

1,014 payments

6 payments

124 payments

11 payments

9 payments

14 payments

3 payments

2 payments

17 payments

1 payment

Under which orders

The 40 largest of 1,194 purchase orders booked to this line.

28 payments · February 10, 2020 to May 29, 2026

14 payments · March 3, 2021 to November 5, 2025

11 payments · April 5, 2021 to January 13, 2023

15 payments · February 6, 2024 to June 16, 2026

28 payments · April 26, 2022 to December 19, 2025

14 payments · April 12, 2023 to June 10, 2026

16 payments · July 20, 2021 to July 8, 2024

17 payments · October 13, 2021 to August 28, 2025

4 payments · December 22, 2020 to January 27, 2021

19 payments · January 2, 2020 to March 20, 2023

21 payments · January 4, 2022 to November 20, 2024

7 payments · April 24, 2019 to October 10, 2019

9 payments · April 6, 2022 to October 23, 2023

9 payments · July 26, 2017 to April 22, 2019

7 payments · November 18, 2019 to December 16, 2019

1 payment · April 14, 2022 to April 14, 2022

3 payments · October 30, 2019 to August 31, 2020

16 payments · June 18, 2020 to June 23, 2020

8 payments · November 16, 2018 to November 21, 2018

3 payments · April 5, 2019 to May 8, 2020

1 payment · July 10, 2019 to July 10, 2019

9 payments · June 18, 2020 to June 24, 2020

9 payments · May 10, 2023 to July 17, 2023

12 payments · April 7, 2020 to June 18, 2020

4 payments · May 7, 2021 to November 30, 2023

7 payments · June 24, 2019 to August 6, 2019

25 payments · August 10, 2020 to December 1, 2020

9 payments · May 2, 2023 to June 14, 2023

16 payments · February 27, 2018 to March 29, 2018

2 payments · May 23, 2018 to June 4, 2018

5 payments · May 22, 2020 to May 26, 2020

3 payments · December 8, 2023 to December 8, 2023

3 payments · April 7, 2020 to April 8, 2020

3 payments · April 29, 2019 to June 12, 2019

6 payments · July 9, 2019 to July 9, 2019

9 payments · August 26, 2020 to September 8, 2020

6 payments · August 8, 2018 to August 22, 2018

3 payments · January 25, 2018 to January 25, 2018

1 payment · August 22, 2019 to August 22, 2019

2 payments · January 26, 2018 to January 26, 2018

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.