SpendingContractsPurchase order

What has the City paid on purchase order SC50CO21138040K?

$1.23M paid to 2 different vendors (the largest, Baker Electric, Inc., received $738.7K) across 17 payments from October 13, 2021 to August 28, 2025, charged to Non-Departmental / High Voltage Conversion Program.

A blanket order, not one firm's contract

2 different vendors draw against this purchase order, so the $1.2M above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

High Voltage Conversion Program

Budget line.

Order description, as published:

ENC $1,665,427.00 HIGH VOLTAGE CONVERSION PROGRAM

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated June 7, 2021.

Paid from

MICLA 2020 Streetlights Financing Construction Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Paid to

Baker Electric, Inc.$739K · 6 payments
Baker Electric Inc$491K · 11 payments

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1October 13, 2021September 23, 202120dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#2$231,159
2October 13, 2021August 26, 202148dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#1$3,381
3November 4, 2021October 26, 20219dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#3$290,028
4December 6, 2021November 24, 202112dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#4$134,637
5January 12, 2022December 20, 202123dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#5$50,595
6January 28, 2022January 21, 20227dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#6$28,851
7March 7, 2022February 23, 202212dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#7$28,547
8April 14, 2022March 23, 202222dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#8$163,674
9May 6, 2022April 27, 20229dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#9$63,076
10May 26, 2022May 17, 20229dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#10$103,052
11August 11, 2022June 24, 202248dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#11$6,943
12August 16, 2022July 22, 202225dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#12$17,635
13August 16, 2022July 22, 202225dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#12$12,255
14September 29, 2022September 21, 20228dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#13$3,219
15August 10, 2023July 27, 202314dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#14$31,292
16August 20, 2025July 24, 202527dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#15 RELEASE OF RETENTION$48,192
17August 28, 2025August 19, 20259dC138040-STREET LIGHTING CONDUIT ONLY PROJ UNIT 10 -PP#16 RELEASE OF RETENTION$13,300

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.