What has the City paid on purchase order SC50CO22138931K?

$1.41M paid to Servitek Electric Inc across 14 payments from December 8, 2021 to October 23, 2023, charged to Non-Departmental / Bel Air-Beverly Crest Unit 1 HV Conversion.

What it was for

Bel Air-Beverly Crest Unit 1 HV Conversion

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

MICLA 2020 Streetlights Financing Construction Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1December 8, 2021November 9, 202129dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#1$114,638
2December 16, 2021December 2, 202114dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#2$152,830
3January 18, 2022January 3, 202215dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#3$169,870
4February 15, 2022February 7, 20228dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#4$189,019
5April 6, 2022March 1, 202236dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#5$156,642
6April 6, 2022March 1, 202236dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#5$53,753
7April 27, 2022April 15, 202212dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#6$73,303
8May 18, 2022May 6, 202212dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#7$44,248
9July 20, 2022June 10, 202240dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#8$158,611
10November 16, 2022October 6, 202241dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#9$117,175
11November 16, 2022October 6, 202241dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#9$69,702
12April 25, 2023March 23, 202333dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#10F$37,699
13October 4, 2023September 27, 20237dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#11F$32,372
14October 23, 2023October 6, 202317dC138931 HV CONVERSION WESTSIDE UNIT 5 - PP#12F$38,022

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.