What has the City spent on Colorado Bridge Undercrossing East Bank Riverway?

$922K across 5 payments, October 28, 2024 to June 22, 2026 — 2 purchase orders and 2 vendors, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: COLORADO BRIDGE UNDERCROSSING EAST BANK RIVERWAY

Spans more than one contract

This budget line has run for 2 fiscal years across 2 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$922KTotal spent
2Purchase orders
2Vendors
87%Largest vendor's share

Spending by fiscal year

FY2024-25
$805K
FY2025-26
$117K

Who was paid

Under which orders

4 payments · October 28, 2024 to December 12, 2024

1 payment · June 22, 2026 to June 22, 2026

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.