What has the City spent on Taylor Yard Bridge Project?
$23.0M across 163 payments, October 29, 2018 to August 18, 2026 — 18 purchase orders and 13 vendors, run by Non-departmental.
As published: TAYLOR YARD BRIDGE PROJECT
This budget line has run for 9 fiscal years across 18 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.
Spending by fiscal year
* FY2026-27 is still in progress — not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $0.
Who was paid
79 payments
12 payments
1 payment
21 payments
2 payments
16 payments
15 payments
1 payment
7 payments
1 payment
6 payments
1 payment
1 payment
Under which orders
79 payments · March 19, 2019 to March 10, 2023
12 payments · June 24, 2019 to August 18, 2023
1 payment · October 29, 2018 to October 29, 2018
21 payments · May 16, 2019 to December 22, 2021
2 payments · April 10, 2019 to April 10, 2019
16 payments · June 24, 2019 to February 23, 2021
15 payments · August 4, 2023 to November 3, 2025
1 payment · November 19, 2019 to November 19, 2019
4 payments · March 9, 2021 to November 9, 2021
1 payment · July 22, 2021 to July 22, 2021
2 payments · March 3, 2022 to June 8, 2022
1 payment · February 28, 2023 to February 28, 2023
1 payment · May 12, 2022 to May 12, 2022
1 payment · August 24, 2022 to August 24, 2022
3 payments · September 22, 2022 to June 13, 2023
1 payment · August 18, 2023 to August 18, 2023
1 payment · August 18, 2026 to August 18, 2026
1 payment · January 26, 2024 to January 26, 2024
Sources