What has the City paid on purchase order SC50CO19131965K?

$21.32M paid to Ortiz Enterprises Inc across 79 payments from March 19, 2019 to March 10, 2023, charged to Non-Departmental / Taylor Yard Bridge Project.

What it was for

Taylor Yard Bridge Project

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Engineering Special Service FD

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1March 19, 2019December 20, 201889d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$110,346
2March 19, 2019March 7, 201912d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$103,015
3April 23, 2019April 12, 201911d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$43,584
4April 23, 2019March 21, 201933d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$5,565
5April 23, 2019March 7, 201947d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$2,739
6April 23, 2019April 12, 201911d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$2,294
7April 23, 2019March 21, 201933d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$293
8June 5, 2019May 20, 201916d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$11,842
9June 6, 2019May 20, 201917d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$254,042
10June 24, 2019June 18, 20196d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$288,109
11June 24, 2019June 18, 20196d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$14,322
12August 1, 2019July 18, 201914d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$81,022
13August 1, 2019July 18, 201914d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$3,422
14September 3, 2019August 20, 201914d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$288,193
15September 3, 2019August 20, 201914d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$15,168
16October 9, 2019September 24, 201915d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$854,239
17October 9, 2019September 24, 201915d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$35,611
18December 4, 2019November 19, 201915d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$58,073
19December 5, 2019November 20, 201915d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$146,496
20December 5, 2019November 20, 201915d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$6,868
21December 17, 2019November 19, 201928d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$2,214
22January 14, 2020December 24, 201921d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$218,754
23January 14, 2020December 24, 201921d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$10,671
24February 18, 2020January 23, 202026d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$37,820
25February 20, 2020January 23, 202028d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$734,581
26March 10, 2020February 20, 202019d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,235,127
27March 10, 2020February 20, 202019d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$64,165
28April 13, 2020March 26, 202018d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$680,076
29April 13, 2020March 26, 202018d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$34,951
30May 11, 2020May 5, 20206d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$53,542
31May 11, 2020May 5, 20206d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,976
32June 8, 2020June 1, 20207d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$5,134
33June 9, 2020May 15, 202025d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$113,537
34June 23, 2020June 17, 20206d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$706,239
35June 23, 2020June 17, 20206d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$36,328
36August 12, 2020July 30, 202013d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$2,768,095
37August 13, 2020July 30, 202014d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$144,847
38September 22, 2020August 24, 202029d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$466,905
39September 22, 2020August 24, 202029d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$23,732
40October 26, 2020October 8, 202018d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,027,806
41October 26, 2020October 8, 202018d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$53,253
42October 28, 2020October 16, 202012d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$519,186
43October 28, 2020October 16, 202012d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$26,483
44December 18, 2020November 18, 202030d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$2,771,056
45December 18, 2020November 18, 202030d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$135,740
46January 7, 2021December 22, 202016d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$130,001
47January 7, 2021December 22, 202016d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$6,842
48February 8, 2021January 25, 202114d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$323,183
49February 8, 2021January 25, 202114d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$17,010
50March 10, 2021February 23, 202115d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$575,231
51March 10, 2021February 23, 202115d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$30,275
52April 13, 2021March 24, 202120d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$176,320
53April 13, 2021March 24, 202120d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$9,280
54May 7, 2021April 23, 202114d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$68,106
55May 11, 2021April 23, 202118d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,294,015
56June 16, 2021May 20, 202127d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,022,231
57June 16, 2021May 20, 202127d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$53,802
58July 16, 2021June 18, 202128d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$10,656
59July 20, 2021June 18, 202132d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$202,472
60October 13, 2021July 27, 202178d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$635,716
61October 13, 2021September 7, 202136d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$350,880
62October 13, 2021September 23, 202120d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$238,432
63October 13, 2021July 27, 202178d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$33,459
64October 13, 2021September 7, 202136d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$18,467
65October 13, 2021September 23, 202120d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$12,549
66December 13, 2021November 9, 202134d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$400,503
67December 13, 2021November 9, 202134d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$21,079
68December 22, 2021December 10, 202112d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$419,841
69December 22, 2021December 10, 202112d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$22,097
70February 1, 2022January 18, 202214d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$31,071
71February 1, 2022January 18, 202214d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION$1,635
72April 21, 2022March 22, 202230d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-49$145,195
73April 22, 2022March 22, 2021396d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-49$7,642
74May 31, 2022May 3, 202228d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-49$66,560
75May 31, 2022May 3, 202228d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-49$3,503
76July 21, 2022June 21, 202230d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-66$326,142
77July 21, 2022June 21, 202230d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-66$17,165
78March 10, 2023January 30, 202339d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-66$432,901
79March 10, 2023January 30, 202339d682/50/50PVCW/WOE1907487/ TAYLOR YARD BRIDGE CONSTRUCTION PRIME & CO'S 3-66$22,784