What has the City spent on Roosevelt Golf Course - Irrigation Replacement?
$1.8M across 155 payments, June 7, 2018 to September 24, 2019 — 15 purchase orders and 8 vendors, run by Recreation and Parks.
As published: ROOSEVELT GOLF COURSE - IRRIGATION REPLACEMENT
This budget line has run for 3 fiscal years across 15 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.
Spending by fiscal year
Who was paid
27 payments
8 payments
43 payments
65 payments
4 payments
6 payments
1 payment
1 payment
Under which orders
26 payments · October 2, 2018 to September 24, 2019
8 payments · April 30, 2019 to June 3, 2019
11 payments · August 14, 2019 to August 14, 2019
32 payments · August 14, 2019 to August 14, 2019
4 payments · January 10, 2019 to January 10, 2019
6 payments · June 13, 2019 to June 13, 2019
19 payments · May 15, 2019 to May 15, 2019
5 payments · May 24, 2019 to May 24, 2019
2 payments · July 16, 2019 to July 16, 2019
1 payment · June 4, 2019 to June 4, 2019
15 payments · May 22, 2019 to May 22, 2019
1 payment · September 24, 2019 to September 24, 2019
2 payments · July 16, 2019 to July 16, 2019
2 payments · September 4, 2019 to September 4, 2019
20 payments · July 11, 2019 to July 11, 2019
Sources
LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.