CheckbookBudget line

What has the City spent on Lar Segment B Urban Runoff Project No 3?

$1.9M across 10 payments, February 9, 2022 to October 23, 2024 — 1 purchase order and 1 vendor, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: LAR SEGMENT B URBAN RUNOFF PROJECT NO 3

$1.9MTotal spent
1Purchase orders
1Vendors
100%Largest vendor's share

Spending by fiscal year

FY2021-22
$1.7M
FY2022-23
$57K
FY2023-24
$138K
FY2024-25
$29K

Who was paid

10 payments

Under which orders

10 payments · February 9, 2022 to October 23, 2024

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.