CheckbookBudget line
What has the City spent on Descanso Drive Storm Drain and Parking?
$187K across 7 payments, March 7, 2019 to May 22, 2019 — 2 purchase orders and 2 vendors, run by Non-departmental.
Checkbook LA · Through Sep 9, 2026
As published: DESCANSO DRIVE STORM DRAIN AND PARKING
$187KTotal spent
2Purchase orders
2Vendors
79%Largest vendor's share
Spending by fiscal year
FY2018-19
$187K
Who was paid
6 payments
1 payment
Under which orders
GAE50BO19021519L$40K
1 payment · March 7, 2019 to March 7, 2019
4 payments · May 6, 2019 to May 20, 2019
Sources
LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.