What has the City spent on Clarts Roof Replacement Project?

$4.2M across 14 payments, May 10, 2024 to April 1, 2026 — 2 purchase orders and 2 vendors, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: CLARTS ROOF REPLACEMENT PROJECT

Spans more than one contract

This budget line has run for 3 fiscal years across 2 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$4.2MTotal spent
2Purchase orders
2Vendors
97%Largest vendor's share

Spending by fiscal year

FY2023-24
$3.7M
FY2024-25
$439K
FY2025-26
$17K

Who was paid

3 payments

Under which orders

11 payments · May 10, 2024 to April 1, 2026

3 payments · June 17, 2024 to February 6, 2025

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.