What has the City paid on purchase order SC50CO24144784K?
$8.00M paid to Green Building Corporation across 41 payments from May 10, 2024 to May 6, 2026, charged to Non-Departmental / Clarts Roof Replacement Project.
What it was for
Clarts Roof Replacement ProjectBudget line carrying the most money, of 2 this order is charged to.
Approval records
- Contract C-144784Award recorded in the City's procurement portal; see below.
Paid from
Central LA Recycling TRFR Stat
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Awarded and paid so far
The City's procurement portal, RAMP, records contract C-144784 (the number embedded in this order's number, SC50CO24144784K) as awarded to Green Building Corporation for $7.5M (request for bid), effective November 16, 2023. This order has paid $8.0M, 107% of that figure.
The award amount and dates are as entered in RAMP; later amendments that change a contract's ceiling or term are not always reflected there, and a contract can be paid through orders not shown on this page. RAMP title: “Central Los Angeles Recycling and Transfer Station (CLARTS) Improvements”. See the award on RAMP
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | May 10, 2024 | April 16, 2024 | 24d | CLARTS ROOF REPLACEMENT IMPROVEMENT PROJECT, | $1,974,466 |
| 2 | May 10, 2024 | March 21, 2024 | 50d | CLARTS ROOF REPLACEMENT IMPROVEMENT PROJECT, | $555,568 |
| 3 | June 13, 2024 | May 21, 2024 | 23d | CLARTS ROOF REPLACEMENT IMPROVEMENT PROJECT, | $1,151,201 |
| 4 | June 20, 2024 | May 21, 2024 | 30d | ENC FROM RQSC 2447R500001 47R/50SX82 $3,816,436 | $233,822 |
| 5 | July 15, 2024 | June 20, 2024 | 25d | ENC FROM RQSC 2447R500001 47R/50SX82 $3,816,436 | $554,777 |
| 6 | October 9, 2024 | August 19, 2024 | 51d | 47R/50SX82 $3,816,436 | $251,468 |
| 7 | October 9, 2024 | September 18, 2024 | 21d | 47R/50SX82 $3,816,436 | $164,184 |
| 8 | October 9, 2024 | July 16, 2024 | 85d | 47R/50SX82 CO 1, 15 TO 19 $155,704.23 | $31,403 |
| 9 | October 9, 2024 | August 19, 2024 | 51d | 47R/50SX82 CO 1, 15 TO 19 $155,704.23 | $3,955 |
| 10 | October 9, 2024 | July 16, 2024 | 85d | 47R/50SX82 $3,816,436 | $1,552 |
| 11 | October 23, 2024 | May 21, 2024 | 155d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $10,391 |
| 12 | October 23, 2024 | June 20, 2024 | 125d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $9,512 |
| 13 | October 28, 2024 | October 18, 2024 | 10d | 47R/50SX82 $3,816,436 | $249,425 |
| 14 | January 29, 2025 | December 31, 2024 | 29d | 47R/50SX82 $3,816,436 | $1,058,017 |
| 15 | January 29, 2025 | January 17, 2025 | 12d | 47R/50SX82 $3,816,436 | $277,547 |
| 16 | January 29, 2025 | January 17, 2025 | 12d | 47R/50SX82 CO 1, 15 TO 19 $155,704.23 | $108,577 |
| 17 | January 29, 2025 | November 19, 2024 | 71d | 47R/50SX82 $3,816,436 | $81,817 |
| 18 | January 29, 2025 | December 31, 2024 | 29d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $16,562 |
| 19 | February 26, 2025 | February 19, 2025 | 7d | 47R/50SX82 $3,816,436 | $232,514 |
| 20 | February 26, 2025 | February 19, 2025 | 7d | 47R/50SX82 CO 1, 15 TO 21 | $25,348 |
| 21 | March 13, 2025 | February 19, 2025 | 22d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $56,556 |
| 22 | April 11, 2025 | March 21, 2025 | 21d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $55,428 |
| 23 | June 5, 2025 | April 18, 2025 | 48d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $65,177 |
| 24 | June 9, 2025 | March 21, 2025 | 80d | 47R/50SX82 $3,816,436 | $56,640 |
| 25 | June 9, 2025 | April 18, 2025 | 52d | 47R/50SX82 $3,816,436 | $31,155 |
| 26 | June 9, 2025 | April 18, 2025 | 52d | 47R/50SX82 CO 23 TO 27 | $29,815 |
| 27 | June 9, 2025 | March 21, 2025 | 80d | 47R/50SX82 CO 23 TO 27 | $4,071 |
| 28 | June 9, 2025 | April 18, 2025 | 52d | 47R/50SX82 CO 1, 15 TO 21 | $1,079 |
| 29 | June 16, 2025 | June 12, 2025 | 4d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $113,991 |
| 30 | June 17, 2025 | June 12, 2025 | 5d | 47R/50SX82 CO 1, 15 TO 21 | $112,841 |
| 31 | June 17, 2025 | June 12, 2025 | 5d | 47R/50SX82 CO 23 TO 27 | $44,977 |
| 32 | June 17, 2025 | June 12, 2025 | 5d | 47R/50SX82 CO 1, 15 TO 21 | $3,983 |
| 33 | June 17, 2025 | June 12, 2025 | 5d | 47R/50SX82 $3,816,436 | $3,610 |
| 34 | November 19, 2025 | September 9, 2025 | 71d | 47R/50SX82 CO 29 & 30 | $63,879 |
| 35 | November 19, 2025 | October 28, 2025 | 22d | 47R/50SX82 $3,816,436 | $11,300 |
| 36 | April 1, 2026 | March 23, 2026 | 9d | CLARTS ROOF REPLACEMENT IMPROVEMENTS PROJECT, CO# 2,3,7,12 TO 15 | $17,243 |
| 37 | April 8, 2026 | March 23, 2026 | 16d | 47R/50SX82 $3,816,436 | $242,180 |
| 38 | April 8, 2026 | March 23, 2026 | 16d | 47R/50SX82 CO 1, 15 TO 21 | $9,176 |
| 39 | April 8, 2026 | March 23, 2026 | 16d | 47R/50SX82 CO 23 TO 27 | $4,151 |
| 40 | April 8, 2026 | March 23, 2026 | 16d | 47R/50SX82 CO 29 & 30 | $3,362 |
| 41 | May 6, 2026 | April 29, 2026 | 7d | 47R/50SX82 $3,816,436 | $79,360 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. Award from RAMP Opportunity Awards (h8mw-iegk), matched on the contract number embedded in this order's number and on the vendor's name. The City's biggest contracts · The checkbook.