CheckbookBudget line
What has the City spent on 2nd Street/LA River Removal and Reuse Urban Flow System?
$1.6M across 26 payments, January 26, 2022 to March 6, 2026 — 2 purchase orders and 2 vendors, run by Non-departmental.
As published: 2ND STREET/LA RIVER REMOVAL AND REUSE URBAN FLOW SYSTEM
This budget line has run for 5 fiscal years across 2 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.
Spending by fiscal year
Who was paid
14 payments
12 payments
Under which orders
14 payments · June 13, 2022 to October 23, 2024
12 payments · January 26, 2022 to March 6, 2026
Sources
LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.