What has the City paid on purchase order SC50CO20115230M?

$4.86M paid to HDR Engineering Inc across 44 payments from April 30, 2020 to August 3, 2022, charged to Non-Departmental / Sidewalk Repair Engineering Consulting Services.

What it was for

Sidewalk Repair Engineering Consulting Services

Budget line carrying the most money, of 3 this order is charged to.

Approval records

  • Contract C-115230Stated in the order's descriptions.

Paid from

Sidewalk and Curb Repair Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1April 30, 2020March 9, 202052dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$205,420
2May 20, 2020March 6, 202075dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$5,950
3May 29, 2020April 20, 202039dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$187,230
4June 10, 2020May 11, 202030dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$199,915
5July 8, 2020May 22, 202047dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$206,172
6July 22, 2020June 22, 202030dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$203,533
7August 12, 2020August 3, 20209dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$269,470
8October 14, 2020October 2, 202012dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$180,703
9November 10, 2020October 20, 202021dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$174,949
10January 6, 2021December 1, 202036dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$170,445
11January 6, 2021December 1, 202036dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$2,311
12January 13, 2021December 15, 202029dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$171,543
13March 3, 2021January 18, 2020410dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$90,845
14March 30, 2021February 21, 202137dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$40,836
15June 21, 2021March 31, 202182dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$26,331
16June 21, 2021March 31, 202182dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$6,949
17June 22, 2021April 21, 202162dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$33,985
18July 21, 2021June 1, 202150dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57 50SKGY$32,257
19July 22, 2021July 2, 202120dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57 50SKGY$34,765
20July 28, 2021June 14, 202144dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57 50SKGY$24,695
21July 28, 2021June 14, 202144dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57$2,386
22October 20, 2021August 20, 202161d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$102,075
23October 20, 2021August 20, 202161d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$41,016
24October 20, 2021August 20, 202161dC-115230 HDR ENGINEERING, INC. E1908609 TOS NO. 57 50SKGY$10,283
25November 23, 2021September 15, 202169d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$116,896
26December 6, 2021October 18, 202149d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$122,646
27December 8, 2021September 15, 202184d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$179,481
28December 8, 2021October 18, 202151d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$134,816
29February 2, 2022November 25, 202169d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$176,195
30February 3, 2022December 10, 202155d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$175,491
31February 4, 2022December 10, 202156d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$128,042
32February 14, 2022November 25, 202181d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$140,206
33April 20, 2022March 15, 202236d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$147,226
34April 25, 2022February 16, 202268d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$158,691
35April 27, 2022March 15, 202243d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$147,575
36May 4, 2022February 16, 202277d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$141,307
37July 11, 2022March 29, 2022104d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$154,249
38July 12, 2022March 29, 2022105d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$158,298
39July 14, 2022March 2, 2022134d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$4,814
40July 15, 2022February 7, 2022158d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$19,986
41July 18, 2022March 29, 2022111d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$2,050
42July 20, 2022April 5, 2022106d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$128,753
43July 22, 2022April 5, 2022108d59V/50/50VKGY/E1908609/NTP 6 DTD 7/7/21$130,319
44August 3, 2022April 5, 2022120d57F/50/50VVBN/E1908609/NTP 5 DTD 7/1/21$69,530

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.