CheckbookVendor
What has the City paid HDR Engineering Inc?
$25.4M in City payments across 253 checks, from July 17, 2017 to September 1, 2026. Outside-vendor scope only — payroll, transfers, debt and pension custody are excluded.
As published: HDR ENGINEERING INC
By fiscal year
Who pays them
What for
110 payments
30 payments
9 payments
13 payments
10 payments
5 payments
13 payments
10 payments
6 payments
4 payments
11 payments
17 payments
* FY2026-27 is still in progress — $177K so far, not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $659K.
Most recent payments
The 25 latest to post. Purpose strings are the Controller's own reference codes — the budget line in the second column is usually the more informative field.
| Date | Budget line | Purpose | Amount |
|---|---|---|---|
| September 1, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $147,466 |
| July 15, 2026 | Engineering Equipment & TrainingNon-departmental | 568/50/50LLHH/NTP#1/TOS#86 | $13,026 |
| July 14, 2026 | Engineering Equipment & TrainingNon-departmental | 568/50/50LLHH/NTP#1/TOS#86 | $14,080 |
| July 14, 2026 | Management Training for Succession PlanningNon-departmental | 682/50/50RVDP/NTP#1/TOS#86 | $2,030 |
| June 23, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $32,159 |
| June 23, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $31,074 |
| June 23, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $19,351 |
| June 17, 2026 | Management Training for Succession PlanningNon-departmental | 682/50/50RVDP/NTP#1/TOS#86 | $47,970 |
| June 15, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $325,668 |
| May 22, 2026 | PRJ-Sepulveda Basin-Lake BalboaCity Administrative Officer | C-134275, SEPULVEDA BASIN LAKE BALBOA IRRIGATION PROJECT, $99,779.00 | $15,419 |
| May 18, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $56,366 |
| May 18, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $19,858 |
| May 13, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $146,809 |
| May 4, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $49,833 |
| April 29, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $67,678 |
| April 9, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/57F/50/50YVBN/E1909339/NTP 6 | $34,591 |
| April 8, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/59V/50/50CVBN/E1909339/NTP 6 | $339,433 |
| April 8, 2026 | Contractual ServicesPublic Works – Engineering | 100/78/003040/NTP #1/TOS #86 | $30,450 |
| March 26, 2026 | Contractual ServicesPublic Works – Engineering | 100/78/003040/NTP #1/TOS #86 | $15,692 |
| March 11, 2026 | PW-Sanitation Expense and EquipmentNon-departmental | TOS S-015_GREEN WASTE PROCESSING FACILITIES PUBLIC OUTREACH & RECHNICAL SERVICES | $26,250 |
| March 2, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | TOS 36A/57F/50/50YVBN/E1909339/NTP 6 | $1,411 |
| February 27, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $91,683 |
| February 27, 2026 | Sidewalk Access Request AccelerationTransportation | TOS 7A/F51Q/94YC09 SIDEWALK REPAIR PROGRAM | $19,053 |
| February 23, 2026 | Sidewalk Repair Engineering Consulting ServicesNon-departmental | $437,447.75 E1909339 TOS 36A/59V/50/50AVBN/BR+NTP 1-2 | $160,375 |
| February 18, 2026 | Contractual ServicesPublic Works – Engineering | 100/78/003040/NTP #1/TOS #86 | $41,663 |
Sources
LA Controller, Checkbook LA (dataset pggv-e4fn), totalled nightly. Figures are every payment on record within the outside-vendor scope, not a single fiscal year. Back to the checkbook.