$522K paid to Ingram Industries Inc across 93 payments from August 17, 2021 to March 4, 2024, charged to Library / Library Materials.

What it was for

Library Materials

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Library

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Library

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 17, 2021July 19, 202129dI0112CON$4,856
2August 17, 2021July 19, 202129dI0112CON$1,276
3August 18, 2021July 26, 202123dI0001CON$212
4August 18, 2021July 26, 202123dI0001CON$9
5September 10, 2021September 2, 20218dI0001CON$184
6September 10, 2021September 2, 20218dI0001CON$3
7September 17, 2021August 30, 202118dI0260CON$2,558
8September 17, 2021August 30, 202118dI0260CON$252
9September 21, 2021September 13, 20218dI0322CON$4,908
10September 21, 2021August 30, 202122dI0261CON$1,873
11September 21, 2021September 13, 20218dI0322CON$320
12September 21, 2021August 30, 202122dI0261CON$112
13September 24, 2021September 7, 202117dI0294CON$4,983
14September 24, 2021September 7, 202117dI0294CON$1,602
15September 24, 2021September 7, 202117dI0319CON$814
16September 24, 2021September 7, 202117dI0319CON$113
17October 15, 2021September 20, 202125dI0363CON$12,647
18October 15, 2021September 20, 202125dI0363CON$1,910
19October 20, 2021September 27, 202123dI0371CON$6,165
20October 20, 2021September 27, 202123dI0372CON$4,494
21October 20, 2021September 27, 202123dI0387CON$3,780
22October 20, 2021September 27, 202123dI0372CON$1,176
23October 20, 2021September 27, 202123dI0371CON$449
24October 20, 2021September 27, 202123dI0387CON$159
25November 4, 2021October 12, 202123dI0444CON$13,986
26November 4, 2021October 12, 202123dI0444CON$5,516
27November 16, 2021October 25, 202122dI0477CON$10,674
28November 16, 2021October 25, 202122dI0477CON$527
29November 16, 2021October 25, 202122dI0001CON$52
30November 16, 2021October 25, 202122dI0001CON$2
31November 30, 2021November 8, 202122dI0463CON$3,751
32November 30, 2021November 8, 202122dI0463CON$472
33December 9, 2021November 15, 202124dI0500CON$10,778
34December 9, 2021November 15, 202124dI0595CON$10,431
35December 9, 2021November 15, 202124dI0568CON$6,789
36December 9, 2021November 15, 202124d1I0567CON$3,891
37December 9, 2021November 15, 202124dI0595CON$3,044
38December 9, 2021November 15, 202124d1I0567CON$1,625
39December 9, 2021November 15, 202124dI0500CON$620
40December 9, 2021November 15, 202124dI0568CON$559
41December 16, 2021November 22, 202124dI0612CON$2,049
42December 16, 2021November 22, 202124dI0612CON$296
43February 2, 2022January 24, 20229dI0003CON$128
44February 2, 2022January 24, 20229dI0003CON$6
45June 22, 2022May 31, 202222dI 1287CON$73,900
46June 23, 2022May 31, 202223dI0411CON$2,347
47June 23, 2022May 31, 202223dI0411CON$105
48August 26, 2022August 1, 202225dI 1405CON$32,141
49August 26, 2022August 1, 202225d4/21/2022; TO EXTEND EXPIRY DATE TO 6/30/2022$17,742
50August 26, 2022August 1, 202225dI 1475CON$15,982
51August 26, 2022August 1, 202225dI 1405CON$14,041
52August 26, 2022August 1, 202225dI 1487CON$10,522
53August 26, 2022August 1, 202225dI 1530CON$9,321
54August 26, 2022August 1, 202225dI 1476CON$4,872
55August 26, 2022August 1, 202225dI 1404CON$4,865
56August 26, 2022August 1, 202225dI 1378CON$4,168
57August 26, 2022August 1, 202225dI 1378CON$3,164
58August 26, 2022August 1, 202225dI 1330CON$2,868
59August 26, 2022August 1, 202225dI 1487CON$2,747
60August 26, 2022August 1, 202225dI 1476CON$2,175
61August 26, 2022August 1, 202225dI 1475CON$1,957
62August 26, 2022August 1, 202225dI 1406CON$1,882
63August 26, 2022August 1, 202225dI 1406CON$826
64August 26, 2022August 1, 202225dI 1530CON$680
65August 26, 2022August 1, 202225dI 1330CON$32
66September 12, 2022August 22, 202221dI 1464CON$4,705
67September 12, 2022August 22, 202221dI 1464CON$1,764
68October 24, 2022September 26, 202228dJ 0078CON$45,365
69October 24, 2022September 26, 202228dJ 0077CON$36,562
70October 24, 2022September 26, 202228dJ 0072CON$18,911
71October 24, 2022September 26, 202228dJ 0078CON$10,291
72October 24, 2022September 26, 202228dJ0075CON$9,286
73October 24, 2022September 26, 202228dJ 0070CON$6,330
74October 24, 2022September 26, 202228dJ 0072CON$6,051
75October 24, 2022September 26, 202228dJ0075CON$3,822
76October 24, 2022September 26, 202228dJ 0076CON$2,204
77October 24, 2022September 26, 202228dJ 0077CON$1,493
78October 24, 2022September 26, 202228dJ 0070CON$1,396
79October 24, 2022September 26, 202228dJ 0076CON$906
80October 28, 2022October 3, 202225dI 380CON$8,611
81October 28, 2022October 3, 202225dI 380CON$516
82October 31, 2022October 3, 202228dJ 0096CON$3,493
83October 31, 2022October 3, 202228dJ 0096CON$1,077
84December 5, 2022November 14, 202221dJ 0171CON$15,946
85December 5, 2022November 14, 202221dJ 0171CON$649
86December 27, 2022December 19, 20228dJ 0172CON$3,913
87December 27, 2022December 19, 20228dJ 0172CON$473
88March 2, 2023January 17, 202344dJ 0580CON$972
89March 2, 2023January 17, 202344dJ 0580CON$162
90December 7, 2023October 23, 202345dK0595CON; CDTFA ($4.71)$50
91December 18, 2023November 20, 202328dK0833CON; CDTFA ($6.84)$72
92December 18, 2023November 20, 202328dNO TAX; CATALOGING & PROCESSING$4
93March 4, 2024January 8, 202456dK1119CON; CDTFA ($10.12)$107