SpendingContractsPurchase order
What has the City paid on purchase order SC21CO25145980Y?
$1.37M paid to El Centro De Ayuda across 35 payments from September 12, 2024 to August 27, 2025, charged to Community Investment for Families Department / Contractual Services.
What it was for
Contractual Services
Budget line carrying the most money, of 3 this order is charged to.
Order description, as published:
C-145980 ECDA FSC
Approval records
- Contract C-145980Stated in the order's descriptions.
Order dated August 30, 2024.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: Community Investment for Families Department
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | September 12, 2024 | September 12, 2024 | 0d | 145980-JUL'24 FSC | $96,012 |
| 2 | September 12, 2024 | September 12, 2024 | 0d | 145980 JUL-AUG'24 EAC ADV | $16,667 |
| 3 | September 16, 2024 | September 12, 2024 | 4d | 145980-AUG'24 ADV FSC | $108,333 |
| 4 | September 23, 2024 | September 16, 2024 | 7d | 145980 ECDA AUG-SEPT'24 FSC ADV | $53,576 |
| 5 | September 23, 2024 | September 16, 2024 | 7d | 145980 ECDA AUG-SEPT'24 FSC ADV | $42,302 |
| 6 | October 17, 2024 | October 16, 2024 | 1d | 145980 SEPT-OCT'24 EAC ADV | $16,667 |
| 7 | October 17, 2024 | October 16, 2024 | 1d | 145980 SEPT-OCT'24 EAC ADV | $8,283 |
| 8 | October 17, 2024 | October 16, 2024 | 1d | 145980 ECDA SEPT-OCT'24 FSC ADV | $5,020 |
| 9 | October 18, 2024 | October 16, 2024 | 2d | 145980 ECDA SEPT-OCT'24 FSC ADV | $108,333 |
| 10 | November 18, 2024 | November 15, 2024 | 3d | ECDA OCT-NOV'24 FSC ADV | $7,317 |
| 11 | November 19, 2024 | November 15, 2024 | 4d | 145980 ECDA OCT-NOV'24 FSC ADV | $108,333 |
| 12 | November 19, 2024 | November 14, 2024 | 5d | 145980 OCT-NOV'24 EAC ADV | $16,667 |
| 13 | November 19, 2024 | November 14, 2024 | 5d | 145980 OCT-NOV'24 EAC ADV | $6,556 |
| 14 | December 17, 2024 | December 13, 2024 | 4d | 145980 NOV-DEC'24 EAC ADV | $17,218 |
| 15 | December 17, 2024 | December 13, 2024 | 4d | 145980 NOV-DEC'24 EAC ADV | $16,667 |
| 16 | December 18, 2024 | December 13, 2024 | 5d | 145980 ECDA NOV-DEC'24 FSC ADV | $61,325 |
| 17 | December 18, 2024 | December 13, 2024 | 5d | 145980 ECDA NOV-DEC'24 FSC ADV | $33,677 |
| 18 | January 21, 2025 | January 16, 2025 | 5d | 145980 ECDA DEC'24-JAN'25 FSC ADV | $7,399 |
| 19 | January 22, 2025 | January 16, 2025 | 6d | 145980 DEC'24 - JAN'25 EAC ADV | $39,169 |
| 20 | January 22, 2025 | January 16, 2025 | 6d | 145980 DEC'24 - JAN'25 EAC ADV | $16,667 |
| 21 | January 23, 2025 | January 16, 2025 | 7d | 145980 ECDA DEC'24-JAN'25 FSC ADV | $108,333 |
| 22 | February 25, 2025 | February 19, 2025 | 6d | 145980 JAN'25-FEB'25 EAC ADV | $3,059 |
| 23 | February 26, 2025 | February 19, 2025 | 7d | 145980 ECDA JAN'25-FEB'25 FSC ADV | $56,698 |
| 24 | February 26, 2025 | February 19, 2025 | 7d | 145980 ECDA JAN'25-FEB'25 FSC ADV | $49,134 |
| 25 | March 20, 2025 | March 18, 2025 | 2d | 145980 FEB-MAR'25 EAC ADV | $16,667 |
| 26 | March 20, 2025 | March 18, 2025 | 2d | 145980 ECDA FEB-MAR'25 FSC ADV | $12,872 |
| 27 | March 20, 2025 | March 18, 2025 | 2d | 145980 FEB-MAR'25 EAC ADV | $5,142 |
| 28 | March 21, 2025 | March 18, 2025 | 3d | 145980 ECDA FEB-MAR'25 FSC ADV | $108,333 |
| 29 | April 22, 2025 | April 17, 2025 | 5d | 145980 ECDA MAR-APR'25 FSC ADV | $98,516 |
| 30 | April 23, 2025 | April 17, 2025 | 6d | 145980 MAR-APR'25 EAC ADV | $7,395 |
| 31 | May 29, 2025 | May 21, 2025 | 8d | 145980 ECDA APR-MAY'25 FSC ADV | $11,739 |
| 32 | July 17, 2025 | June 26, 2025 | 21d | C-145980 ECDA GF F1000001 FY25 | $10,320 |
| 33 | August 12, 2025 | August 1, 2025 | 11d | 145980 ECDA JUNE'25 EAC | $294 |
| 34 | August 27, 2025 | August 6, 2025 | 21d | 145980 ECDA JUNE'25 FSC | $64,621 |
| 35 | August 27, 2025 | August 6, 2025 | 21d | 145980 ECDA JUNE'25 FSC | $27,485 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.