$1.16M paid to Watts Labor Community Action Committee across 57 payments from November 4, 2025 to September 3, 2026, charged to Aging / Home Delivered Meals III C2.
What it was for
Home Delivered Meals III C2
Budget line carrying the most money, of 8 this order is charged to.
Order description, as published:
SC: WLCAC-SW OAA CO203154 FY2025-26
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated October 31, 2025.
Paid from
Area Plan for the Aging Tit 7
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Aging
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | November 4, 2025 | October 23, 2025 | 12d | 02_AUG 25 3C2 SW | $54,727 |
| 2 | November 4, 2025 | October 23, 2025 | 12d | 03_SEP 25 3C2 SW | $40,867 |
| 3 | November 4, 2025 | October 23, 2025 | 12d | 01_JUL 25 3C2 SW | $26,848 |
| 4 | November 4, 2025 | October 30, 2025 | 5d | 02_AUG 25 PROP A SW | $21,487 |
| 5 | November 4, 2025 | October 30, 2025 | 5d | 03_SEP 25 PROP A SW | $15,862 |
| 6 | November 4, 2025 | October 30, 2025 | 5d | 01_JUL 25 PROP A SW | $10,015 |
| 7 | November 6, 2025 | October 23, 2025 | 14d | 02_AUG 25 3C1 SW | $26,854 |
| 8 | November 6, 2025 | October 23, 2025 | 14d | 03_SEP 25 3C1 SW | $19,148 |
| 9 | November 6, 2025 | October 23, 2025 | 14d | 01_JUL 25 3C1 SW | $12,359 |
| 10 | November 6, 2025 | October 23, 2025 | 14d | 02_AUG 25 3B SW | $8,731 |
| 11 | November 6, 2025 | October 23, 2025 | 14d | 01_JUL 25 3B SW | $6,442 |
| 12 | November 6, 2025 | October 23, 2025 | 14d | 03_SEP 25 3B SW | $5,647 |
| 13 | November 25, 2025 | November 19, 2025 | 6d | 04_OCT 25 3C2 SW | $36,957 |
| 14 | November 25, 2025 | November 19, 2025 | 6d | 04_OCT 25 3B SW | $17,661 |
| 15 | November 25, 2025 | November 19, 2025 | 6d | 04_OCT 25 3C1 SW | $14,308 |
| 16 | December 4, 2025 | November 19, 2025 | 15d | 04_OCT 25 PROP A SW | $19,105 |
| 17 | December 26, 2025 | December 18, 2025 | 8d | 05_NOV 25 PROP A SW | $18,641 |
| 18 | December 26, 2025 | December 18, 2025 | 8d | 05_NOV 25 3C1 SW | $13,307 |
| 19 | December 26, 2025 | December 18, 2025 | 8d | 05_NOV 25 3B SW | $8,422 |
| 20 | December 26, 2025 | December 18, 2025 | 8d | 05_NOV 25 3C2 SW | $7,053 |
| 21 | January 7, 2026 | December 18, 2025 | 20d | 05_NOV 25 3C2 CGF SW | $29,941 |
| 22 | February 11, 2026 | January 27, 2026 | 15d | 06_DEC 25 3C2 CGF SW | $46,007 |
| 23 | February 11, 2026 | January 27, 2026 | 15d | 06_DEC 25 3C1 SW | $21,360 |
| 24 | February 11, 2026 | January 27, 2026 | 15d | 06_DEC 25 PROP A SW | $16,325 |
| 25 | February 11, 2026 | January 27, 2026 | 15d | 06_DEC 25 3B SW | $14,341 |
| 26 | March 13, 2026 | February 10, 2026 | 31d | 07_JAN 26 3C2 CGF SW | $44,281 |
| 27 | March 13, 2026 | March 11, 2026 | 2d | 07_JAN 26 PROP A SW | $24,499 |
| 28 | March 13, 2026 | February 10, 2026 | 31d | 07_JAN 26 3C1 SW | $24,012 |
| 29 | March 13, 2026 | February 10, 2026 | 31d | 07_JAN 26 3B SW | $11,347 |
| 30 | March 13, 2026 | February 10, 2026 | 31d | 07_JAN 26 3C2 STATE SW | $7,155 |
| 31 | April 1, 2026 | March 18, 2026 | 14d | 08_FEB 26 3C2 STATE SW | $39,846 |
| 32 | April 1, 2026 | March 18, 2026 | 14d | 08_FEB 26 PROP A SW | $16,640 |
| 33 | April 1, 2026 | March 18, 2026 | 14d | 08_FEB 26 3C1 SW | $16,556 |
| 34 | April 1, 2026 | March 18, 2026 | 14d | 08_FEB 26 3B SW | $7,881 |
| 35 | April 23, 2026 | April 20, 2026 | 3d | 09_MAR 26 3C2 STATE SW | $49,431 |
| 36 | April 23, 2026 | April 20, 2026 | 3d | 09_MAR 26 3C1 SW | $22,919 |
| 37 | April 29, 2026 | April 23, 2026 | 6d | 09_MAR 26 PROP A SW | $18,407 |
| 38 | April 29, 2026 | April 23, 2026 | 6d | 09_MAR 26 3B SW | $9,402 |
| 39 | May 20, 2026 | May 13, 2026 | 7d | 10_APR 26 3C2 STATE SW | $40,463 |
| 40 | May 20, 2026 | May 13, 2026 | 7d | 10_APR 26 3C1 SW | $16,906 |
| 41 | May 20, 2026 | May 13, 2026 | 7d | 10_APR 26 PROP A SW | $14,227 |
| 42 | May 20, 2026 | May 13, 2026 | 7d | 10_APR 26 3B SW | $10,632 |
| 43 | July 23, 2026 | July 15, 2026 | 8d | 203154_MAY 26_IIIC1 SW | $21,021 |
| 44 | July 23, 2026 | July 15, 2026 | 8d | 203154_MAY 26_IIIB SW | $18,126 |
| 45 | August 21, 2026 | July 30, 2026 | 22d | 203154_JUN 26_IIIB CGF SW | $4,908 |
| 46 | August 21, 2026 | July 20, 2026 | 32d | 203154_MAY 26_IIIC2 TRUST SW | $1,032 |
| 47 | August 24, 2026 | July 30, 2026 | 25d | 203154_JUN 26_IIIB SW | $36,252 |
| 48 | August 24, 2026 | July 20, 2026 | 35d | 203154_MAY 26_IIIC2 STATE SW | $30,274 |
| 49 | August 24, 2026 | July 30, 2026 | 25d | 203154_JUN 26_PROP A SW | $25,541 |
| 50 | August 24, 2026 | July 6, 2026 | 49d | 203154_MAY 26_PROP A SW | $21,751 |
| 51 | August 24, 2026 | July 20, 2026 | 35d | 203154_MAY 26_IIIC2 NSIP SW | $20,326 |
| 52 | August 24, 2026 | July 30, 2026 | 25d | 203154_JUN 26_IIIC2 OTO SW | $2,592 |
| 53 | August 24, 2026 | July 30, 2026 | 25d | 203154_JUN 26_IIIC2 STATE SW | $703 |
| 54 | September 1, 2026 | August 5, 2026 | 27d | 203154_JUN 26_IIIC1 CGF SW | $34,044 |
| 55 | September 2, 2026 | August 5, 2026 | 28d | 203154_JUN 26_IIIC1 SW | $29,767 |
| 56 | September 2, 2026 | August 5, 2026 | 28d | 203154_JUN 26_IIIC1 OTO SW | $4,705 |
| 57 | September 3, 2026 | July 15, 2026 | 50d | 203154_MAY 26_IIIC1 NSIP SW | $21,517 |