$2.14M paid to St Barnabas Senior Center of Los Angeles across 72 payments from December 9, 2024 to August 29, 2025, charged to Aging / Home Delivered Meals III C2.

What it was for

Home Delivered Meals III C2

Budget line carrying the most money, of 7 this order is charged to.

Order description, as published:

SC: SBSC-CITY OAA CO146296 FY2425

Approval records

  • Contract C-146296Award recorded in the City's procurement portal; see below.

Order dated October 10, 2024.

Paid from

Area Plan for the Aging Tit 7

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Aging

Awarded and paid so far

The City's procurement portal, RAMP, records contract C-146296 (the number embedded in this order's number, SC02CO25146296Y) as awarded to St. Barnabas Senior Center of Los Angeles for $2.3M (request for proposal). This order has paid $2.1M, 92% of that figure.

The award amount and dates are as entered in RAMP; later amendments that change a contract's ceiling or term are not always reflected there, and a contract can be paid through orders not shown on this page. RAMP title: “Multipurpose Senior Center Social Services, Nutrition, Transportation, and Evidence Based Programs for Older Adults”. See the award on RAMP

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1December 9, 2024November 5, 202434d01_JUL 24 3C1 CITY$66,195
2December 9, 2024November 5, 202434d01_JUL 24 3C1 NSIP CITY$4,647
3December 10, 2024November 12, 202428d02_AUG 24 3C1 CITY$65,684
4December 10, 2024November 12, 202428d02_AUG 24 3C1 NSIP CITY$4,647
5December 11, 2024November 19, 202422d03_SEP 24 3C2 CITY$31,000
6December 11, 2024November 19, 202422d03_SEP 24 3C2 NSIP CITY$3,943
7January 15, 2025December 10, 202436d04_OCT 24 3C2 CITY$51,141
8January 15, 2025December 10, 202436d04_OCT 24 3C2 NSIP CITY$3,287
9January 28, 2025December 26, 202433d03_SEP 24 3C1 CITY$39,980
10January 28, 2025December 3, 202456d04_OCT 24 3C1 CGF CITY$30,433
11January 28, 2025December 3, 202456d04_OCT 24 3C1CITY$14,406
12January 28, 2025December 26, 202433d03_SEP 24 3C1 STATE CITY$10,323
13January 28, 2025December 3, 202456d04_OCT 24 3C1 NSIP CITY$4,647
14January 28, 2025December 26, 202433d03_SEP 24 3C1 NSIP CITY$4,646
15February 5, 2025December 20, 202447d05_NOV 24 3C1 CITY$39,441
16February 5, 2025December 20, 202447d05_NOV 24 3C1 STATE CITY$17,790
17February 5, 2025December 20, 202447d05_NOV 24 3C1 NSIP CITY$4,646
18February 6, 2025December 17, 202451d05_NOV 24 3C2 CITY$78,390
19February 6, 2025December 17, 202451d05_NOV 24 3C2 NSIP CITY$3,943
20February 12, 2025January 21, 202522d05_NOV 24 PROP A CITY$21,099
21February 12, 2025January 21, 202522d03_SEP 24 PROP A CITY$15,763
22February 12, 2025January 22, 202521d06_DEC 24 PROP A CITY$14,263
23February 12, 2025January 21, 202522d04_OCT 24 PROP A CITY$14,203
24February 12, 2025January 21, 202522d02_AUG 24 PROP A CITY$14,132
25February 12, 2025January 21, 202522d01_JUL 24 PROP A CITY$13,391
26February 21, 2025January 22, 202530d06_DEC 24 3C2 CITY$47,790
27February 21, 2025January 22, 202530d06_DEC 24 3C1 STATE CITY$16,401
28February 21, 2025January 22, 202530d06_DEC 24 3C1 CITY$9,854
29February 21, 2025January 22, 202530d06_DEC 24 3C1 NSIP CITY$4,646
30February 21, 2025January 22, 202530d06_DEC 24 3C2 NSIP CITY$3,943
31April 3, 2025February 11, 202551d07_JAN 25 3C2 CITY$63,294
32April 3, 2025March 18, 202516d08_FEB 25 IIIB CITY$41,930
33April 3, 2025March 10, 202524d07_JAN 25 IIIB CITY$41,317
34April 3, 2025February 11, 202551d07_JAN 25 IIIC1 STATE CITY$15,511
35April 3, 2025February 11, 202551d07_JAN 25 IIIC1 CITY$10,665
36April 3, 2025March 18, 202516d08_FEB 25 IIIC1 CGF CITY$7,280
37April 3, 2025February 11, 202551d07_JAN 25 IIIC1 NSIP CITY$5,576
38April 3, 2025March 18, 202516d08_FEB 25 IIIC1 STATE CITY$4,239
39April 3, 2025February 11, 202551d07_JAN 25 3C2 NSIP CITY$3,943
40April 3, 2025March 18, 202516d08_FEB 25 IIIC1 CITY$3,588
41April 14, 2025March 18, 202527d08_FEB 25 IIIC2 CITY$37,831
42April 14, 2025March 18, 202527d08_FEB 25 IIIC2 STATE CITY$31,566
43April 14, 2025March 18, 202527d08_FEB 25 PROP A CITY$22,641
44April 14, 2025April 3, 202511d07_JAN 25 PROP A CITY$15,706
45May 16, 2025April 17, 202529d09_MARCH 25 PROP A CITY$12,583
46May 19, 2025April 24, 202525d09_MAR 25 CGF IIIC2 CITY$51,616
47May 19, 2025April 22, 202527d09_MARCH 25 IIIB CITY$38,970
48May 19, 2025April 22, 202527d09_MARCH 25 IIIC1 CITY$30,882
49May 19, 2025April 24, 202525d09_MARCH 25 IIIC2 CITY$12,163
50May 19, 2025April 24, 202525d09_MARCH 25 IIIC2 NSIP CITY$2,030
51June 9, 2025May 23, 202517d10_APR 25 IIIB CGF CITY$3,000
52June 11, 2025May 23, 202519d10_APR 25 IIIC1 CITY$76,168
53June 11, 2025May 23, 202519d10_APR 25 IIIC1 STATE CITY$13,149
54June 11, 2025May 23, 202519d10_APR 25 IIIC1 NSIP CITY$1,000
55June 13, 2025May 27, 202517d10_APR 25 IIIC2 STATE CITY$422,246
56June 13, 2025May 27, 202517d10_APR 25 IIIC2 CGF CITY$172,538
57June 13, 2025May 23, 202521d10_APR 25 IIIB CITY$69,215
58June 13, 2025May 23, 202521d10_APR 25 PROP A CITY$48,784
59June 13, 2025May 27, 202517d10_APR 25 IIIC2 CITY$16,177
60June 13, 2025May 27, 202517d10_APR 25 IIIC2 NSIP CITY$3,280
61July 31, 2025July 10, 202521d11_MAY 25 IIIB CITY$35,391
62July 31, 2025July 10, 202521d11_MAY 25 IIIB CGF CITY$5,040
63August 1, 2025July 22, 202510d12_JUNE 25 PROP A CITY$30,639
64August 28, 2025July 22, 202537d12_JUNE 25 IIIC1 CGF CITY$34,825
65August 28, 2025July 22, 202537d12_JUNE 25 IIIC2 CGF CITY$23,012
66August 29, 2025July 22, 202538d12_JUNE 25 IIIB OTO CITY$26,482
67August 29, 2025July 22, 202538d12_JUNE 25 IIIB CITY$26,465
68August 29, 2025July 22, 202538d12_JUNE 25 IIIC1 OTO CITY$9,112
69August 29, 2025July 22, 202538d12_JUNE 25 IIIC2 OTO CITY$4,565
70August 29, 2025July 22, 202538d12_JUNE 25 IIIC2 CITY$3,280
71August 29, 2025July 22, 202538d12_JUNE 25 IIIC1 STATE CITY$2,133
72August 29, 2025July 22, 202538d12_JUNE 25 IIIC1 CITY$1,009

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. Award from RAMP Opportunity Awards (h8mw-iegk), matched on the contract number embedded in this order's number and on the vendor's name. The City's biggest contracts · The checkbook.