SpendingContractsPurchase order
What has the City paid on purchase order CPO40180000494617?
$438K paid to Zeco Systems, Inc dba Greenlots across 15 payments from November 13, 2018 to July 18, 2019, charged to General Services / Electric Vehicle Infrastructire-Citywide.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated May 31, 2018.
Paid from
MICLA Lease Rev Com Paper Ntes
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: General Services
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | November 13, 2018 | October 18, 2018 | 26d | INSTALL, EV CHARGING EQUIPMENT | $94,300 |
| 2 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $71,263 |
| 3 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $36,047 |
| 4 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $10,350 |
| 5 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $6,325 |
| 6 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $5,896 |
| 7 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $5,049 |
| 8 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $3,089 |
| 9 | November 16, 2018 | September 20, 2018 | 57d | EV CHARGING EQUIPMENT | $841 |
| 10 | December 10, 2018 | November 16, 2018 | 24d | INSTALL, EV CHARGING EQUIPMENT | $141,450 |
| 11 | December 10, 2018 | November 16, 2018 | 24d | INSTALL, EV CHARGING EQUIPMENT | $17,700 |
| 12 | December 27, 2018 | October 19, 2018 | 69d | INSTALL, EV CHARGING EQUIPMENT | $6,400 |
| 13 | June 13, 2019 | June 13, 2019 | 0d | INSTALL, EV CHARGING EQUIPMENT | $11,800 |
| 14 | July 18, 2019 | June 24, 2019 | 24d | INSTALL, EV CHARGING EQUIPMENT | $25,304 |
| 15 | July 18, 2019 | June 24, 2019 | 24d | EV CHARGING EQUIPMENT | $2,175 |