CheckbookVendor
What has the City paid Powerscreen of Northern California?
$2.4M in City payments across 20 checks, from December 14, 2022 to April 15, 2026. Outside-vendor scope only — payroll, transfers, debt and pension custody are excluded.
Checkbook LA · Through Sep 9, 2026
As published: POWERSCREEN OF NORTHERN CALIFORNIA
$2.4MTotal paid
20Payments
$119,940Average payment
FY2022-23Peak full year · $1.2M
By fiscal year
FY2022-23
$1.2M
FY2023-24
$1.2M
FY2024-25
$6K
FY2025-26
$4K
Who pays them
What for
4 payments
4 payments
Field Equipment Expense$8K
9 payments
Operating Supplies$2K
3 payments
Most recent payments
The 25 latest to post. Purpose strings are the Controller's own reference codes — the budget line in the second column is usually the more informative field.
| Date | Budget line | Purpose | Amount |
|---|---|---|---|
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE -8.5.1-1/8 | $1,010 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE -8X5 3/8OPG | $872 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE -8.5.2-1/2 | $785 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE -5.3.1-1/8 | $489 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE -5X3X3/8" OPG | $418 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | SCREEN FOR IMPACT CRUSHER MACHINE - 5X3X2 1/2" OPG | $379 |
| April 15, 2026 | Field Equipment ExpensePublic Works – Street Services | FEDEX FREIGHT | $298 |
| January 16, 2025 | Operating SuppliesPublic Works – Street Services | WIRE MESH SCREEN 8.5. UN | $1,033 |
| January 16, 2025 | Operating SuppliesPublic Works – Street Services | WIRE MESH SCREEN 3.5.1 UN | $808 |
| January 16, 2025 | Operating SuppliesPublic Works – Street Services | FREIGHT CHARGES | $263 |
| December 2, 2024 | Field Equipment ExpenseGeneral Services | PART# 60553678_MK00A PH3300 PH3300 FEEDER | $3,895 |
| December 2, 2024 | Field Equipment ExpenseGeneral Services | FREIGHT CHARGES | $215 |
| February 27, 2024 | BSS Equipment & VehiclesGeneral Services | EQUIPMENT, TROMMEL SCREEN, ROCK CRUSHER | $1,023,825 |
| February 27, 2024 | BSS Equipment & VehiclesGeneral Services | A) TRACKED CONVEYOR | $158,775 |
| February 27, 2024 | BSS Equipment & VehiclesGeneral Services | B) DUST SUPPRESS PUMP | $6,570 |
| February 27, 2024 | BSS Equipment & VehiclesGeneral Services | FREIGHT/DELIVERY | $5,000 |
| December 14, 2022 | GSD Vehicle and Equipment ReplacementGeneral Services | EQUIPMENT, TROMMEL SCREEN, ROCK CRUSHER | $1,023,825 |
| December 14, 2022 | GSD Vehicle and Equipment ReplacementGeneral Services | A) TRACKED CONVEYOR | $158,775 |
| December 14, 2022 | GSD Vehicle and Equipment ReplacementGeneral Services | B) PUMP | $6,570 |
| December 14, 2022 | GSD Vehicle and Equipment ReplacementGeneral Services | FREIGHT CHARGE | $5,000 |
Sources