CheckbookVendor
What has the City paid Convergint Technologies LLC,?
$8.7M in City payments across 51 checks, from April 24, 2018 to August 26, 2026. Outside-vendor scope only — payroll, transfers, debt and pension custody are excluded.
As published: CONVERGINT TECHNOLOGIES LLC,
The Controller records vendor names as free text, so this firm appears under 2 different spellings. They are added together here, and listed in full so the arithmetic is checkable:
- CONVERGINT TECHNOLOGIES LLC
- CONVERGINT TECHNOLOGIES LLC,
By fiscal year
Who pays them
What for
35 payments
7 payments
9 payments
* FY2026-27 is still in progress — $238K so far, not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $897K.
Most recent payments
The 25 latest to post. Purpose strings are the Controller's own reference codes — the budget line in the second column is usually the more informative field.
| Date | Budget line | Purpose | Amount |
|---|---|---|---|
| August 26, 2026 | Contractual ServicesLibrary | AUG 2026 PROGRESS BILLING | $75,000 |
| August 20, 2026 | Contractual ServicesLibrary | INSTALL PATHWAYS AND BRANCH CIRCUITS | $16,362 |
| August 20, 2026 | Contractual ServicesLibrary | SPECIALIST PROGRAM TESTING + COORD FEE | $1,261 |
| August 19, 2026 | Contractual ServicesLibrary | ID BADGE CARDS + MAINTENANCE | $10,651 |
| August 19, 2026 | Contractual ServicesLibrary | SECURITY HARDWARE SPECIALIST TESTING + VEHICLE CHARGE | $4,184 |
| August 19, 2026 | Contractual ServicesLibrary | SECURITY HARDWARE TECH + VEHICLE CHARGE | $892 |
| August 19, 2026 | Contractual ServicesLibrary | SECURITY HARDWARE TECH + VEHICLE CHARGE | $892 |
| August 6, 2026 | Contractual ServicesLibrary | JULY 2026 PROGRESS BILLING | $78,744 |
| July 10, 2026 | Contractual ServicesLibrary | JUNE 2026 PROGRESS BILLING | $50,000 |
| June 10, 2026 | Contractual ServicesLibrary | INSTALL PATHWAYS AND BRANCH CIRCUITS | $16,362 |
| June 5, 2026 | Contractual ServicesLibrary | MAY 2026 PROGRESS BILLING | $127,160 |
| May 1, 2026 | Contractual ServicesLibrary | WILMINGTON - INSTALL AND PROGRAM CONDUIT | $16,436 |
| April 29, 2026 | Contractual ServicesLibrary | APRIL 2026 PROGRESS BILLING | $295,479 |
| April 6, 2026 | Maintenance Materials, Supplies & ServicesZoo | JAGUAR EXHIBIT FIRE ALARM MONITORING SERVICE FROM 3-25-26 TO 3-24-27 | $720 |
| March 27, 2026 | Contractual ServicesLibrary | MARCH 2026 PROGRESS BILLING | $274,387 |
| March 5, 2026 | Contractual ServicesLibrary | 2/1 - 2/28/26 PROGRESS BILLING | $268,672 |
| February 17, 2026 | Contractual ServicesLibrary | 1/1 - 1/31/26 PROGRESS BILLING | $210,524 |
| February 13, 2026 | Contractual ServicesLibrary | INSTALL AXIS ANSWERING INTERCOMS | $1,560 |
| January 15, 2026 | Contractual ServicesLibrary | 12/1 - 12/31/25 PROGRESS BILLING | $234,808 |
| December 16, 2025 | Contractual ServicesLibrary | 11/1 - 11/30/25 PROGRESS BILLING | $249,117 |
| November 10, 2025 | Contractual ServicesLibrary | 10/1 - 10/31/25 PROGRESS BILLING | $186,473 |
| October 23, 2025 | Contractual ServicesLibrary | 9/1 - 9/30/25 PROGRESS BILLING | $186,520 |
| October 21, 2025 | Contractual ServicesLibrary | TO INSTALL WALL MOUNT CABINET AND FIBER BACBONE AT LAPL | $11,295 |
| September 10, 2025 | Contractual ServicesLibrary | 8/1 - 8/31/25 PROGRESS BILLING | $199,503 |
| August 19, 2025 | Contractual ServicesLibrary | 7/1 - 7/31/25 PROGRESS BILLING | $305,507 |
Sources
LA Controller, Checkbook LA (dataset pggv-e4fn), totalled nightly. Figures are every payment on record within the outside-vendor scope, not a single fiscal year. Back to the checkbook.