What has the City spent on Vision Zero Education and Outreach?

$4.4M across 100 payments, February 21, 2019 to July 31, 2026 — 13 purchase orders and 12 vendors, run by Transportation.

Checkbook LA · Through Sep 9, 2026

As published: VISION ZERO EDUCATION AND OUTREACH

Spans more than one contract

This budget line has run for 9 fiscal years across 13 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$4.4MTotal spent
13Purchase orders
12Vendors
29%Largest vendor's share

Spending by fiscal year

FY2018-19
$154K
FY2019-20
$671K
FY2020-21
$51K
FY2021-22
$19K
FY2022-23
$553K
FY2023-24
$572K
FY2024-25
$1.1M
FY2025-26
$1.1M
FY2026-27 *
$221K

* FY2026-27 is still in progress — not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $217K.

Who was paid

Under which orders

14 payments · August 26, 2025 to July 31, 2026

11 payments · December 19, 2023 to October 9, 2024

24 payments · April 5, 2019 to April 28, 2021

27 payments · September 1, 2022 to March 27, 2024

7 payments · April 7, 2023 to August 23, 2024

1 payment · September 23, 2024 to September 23, 2024

4 payments · April 29, 2019 to January 9, 2020

1 payment · February 21, 2019 to February 21, 2019

3 payments · June 9, 2023 to June 9, 2023

1 payment · June 22, 2022 to June 22, 2022

2 payments · November 18, 2021 to February 17, 2022

4 payments · December 30, 2024 to December 30, 2024

1 payment · September 12, 2022 to September 12, 2022

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.