CheckbookBudget line

What has the City spent on Sixth Street Viaduct Project?

$2.2M across 19 payments, December 27, 2018 to January 20, 2026 — 3 purchase orders and 3 vendors, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: SIXTH STREET VIADUCT PROJECT

Spans more than one contract

This budget line has run for 3 fiscal years across 3 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$2.2MTotal spent
3Purchase orders
3Vendors
72%Largest vendor's share

Spending by fiscal year

FY2018-19
$291K
FY2019-20
$330K
FY2025-26
$1.6M

Who was paid

Under which orders

6 payments · August 12, 2025 to January 20, 2026

5 payments · December 27, 2018 to January 2, 2020

7 payments · October 8, 2019 to March 24, 2020

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.