CheckbookBudget line

What has the City spent on Sanborn Avenue Retaining Wall Replacement?

$68K across 2 payments, July 14, 2017 to October 17, 2017 — 1 purchase order and 1 vendor, run by Non-departmental.

Checkbook LA · Through Sep 9, 2026

As published: SANBORN AVENUE RETAINING WALL REPLACEMENT

$68KTotal spent
1Purchase orders
1Vendors
100%Largest vendor's share

Spending by fiscal year

FY2017-18
$68K

Who was paid

2 payments

Under which orders

2 payments · July 14, 2017 to October 17, 2017

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.