CheckbookBudget line

What has the City spent on Lincoln Park Pool & Bathhouse Replacement?

$2.4M across 13 payments, May 4, 2018 to December 4, 2018 — 2 purchase orders and 1 vendor, run by Recreation and Parks.

Checkbook LA · Through Sep 9, 2026

As published: LINCOLN PARK POOL & BATHHOUSE REPLACEMENT

Spans more than one contract

This budget line has run for 2 fiscal years across 2 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$2.4MTotal spent
2Purchase orders
1Vendors
100%Largest vendor's share

Spending by fiscal year

FY2017-18
$1.3M
FY2018-19
$1.0M

Who was paid

13 payments

Under which orders

7 payments · May 4, 2018 to August 6, 2018

6 payments · August 6, 2018 to December 4, 2018

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.