What has the City spent on Ita Simulcast Trunk Radio System Replacement?
$3.6M across 138 payments, December 27, 2023 to August 5, 2026 — 4 purchase orders and 1 vendor, run by Information Technology Agency.
As published: ITA SIMULCAST TRUNK RADIO SYSTEM REPLACEMENT
This budget line has run for 4 fiscal years across 4 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.
Spending by fiscal year
* FY2026-27 is still in progress — not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $0.
Who was paid
138 payments
Under which orders
29 payments · March 20, 2024 to April 8, 2025
45 payments · December 27, 2023 to August 5, 2026
63 payments · November 27, 2024 to November 27, 2024
1 payment · January 27, 2025 to January 27, 2025
Sources
LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.