What has the City spent on Hollywood East/Vermont Medians Project?
$274K across 5 payments, February 5, 2019 to October 26, 2020 — 1 purchase order and 1 vendor, run by Transportation.
Checkbook LA · Through Sep 9, 2026
As published: HOLLYWOOD EAST/VERMONT MEDIANS PROJECT
$274KTotal spent
1Purchase orders
1Vendors
100%Largest vendor's share
Spending by fiscal year
FY2018-19
$252K
FY2019-20
$5K
FY2020-21
$17K
Who was paid
Griffith Company$274K
5 payments
Under which orders
SC94MSACO16127311K$274K
5 payments · February 5, 2019 to October 26, 2020