What has the City spent on Exposition Blvd Bike Path Phase 2?

$2.9M across 43 payments, October 18, 2018 to July 24, 2026 — 10 purchase orders and 23 vendors, run by Transportation.

Checkbook LA · Through Sep 9, 2026

As published: EXPOSITION BLVD BIKE PATH PHASE 2

Spans more than one contract

This budget line has run for 7 fiscal years across 10 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$2.9MTotal spent
10Purchase orders
23Vendors
43%Largest vendor's share

Spending by fiscal year

FY2018-19
$1.2M
FY2019-20
$205K
FY2020-21
$111K
FY2021-22
$270K
FY2023-24
$144K
FY2024-25
$890K
FY2026-27 *
$14K

* FY2026-27 is still in progress — not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $0.

Who was paid

LACMTA$1.2M

1 payment

1 payment

1 payment

2 payments

2 payments

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

1 payment

Under which orders

1 payment · February 13, 2019 to February 13, 2019

30 payments · October 7, 2019 to June 7, 2024

1 payment · August 2, 2024 to August 2, 2024

1 payment · September 19, 2024 to September 19, 2024

1 payment · August 30, 2024 to August 30, 2024

1 payment · September 26, 2023 to September 26, 2023

3 payments · October 30, 2023 to November 21, 2023

1 payment · July 24, 2026 to July 24, 2026

1 payment · October 18, 2018 to October 18, 2018

1 payment · September 6, 2019 to September 6, 2019

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.