CheckbookBudget line

What has the City spent on Capital Program - Figueroa Plaza Buildings?

$1.2M across 14 payments, December 11, 2024 to April 22, 2026 — 2 purchase orders and 1 vendor, run by General Services.

Checkbook LA · Through Sep 9, 2026

As published: CAPITAL PROGRAM - FIGUEROA PLAZA BUILDINGS

Spans more than one contract

This budget line has run for 2 fiscal years across 2 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$1.2MTotal spent
2Purchase orders
1Vendors
100%Largest vendor's share

Spending by fiscal year

FY2024-25
$353K
FY2025-26
$847K

Who was paid

14 payments

Under which orders

7 payments · August 6, 2025 to April 22, 2026

7 payments · December 11, 2024 to July 29, 2025

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.