What has the City spent on Broadway Streetscape Project?

$636K across 117 payments, July 27, 2017 to October 11, 2024 — 4 purchase orders and 5 vendors, run by Transportation.

Checkbook LA · Through Sep 9, 2026

As published: BROADWAY STREETSCAPE PROJECT

Spans more than one contract

This budget line has run for 5 fiscal years across 4 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$636KTotal spent
4Purchase orders
5Vendors
37%Largest vendor's share

Spending by fiscal year

FY2017-18
$140K
FY2018-19
$208K
FY2019-20
$192K
FY2020-21
$21K
FY2024-25
$76K

Who was paid

Under which orders

37 payments · September 26, 2017 to May 27, 2020

38 payments · July 27, 2017 to August 5, 2020

36 payments · August 4, 2017 to August 5, 2020

5 payments · October 11, 2024 to October 11, 2024

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.