What has the City spent on ATSAC Enhance for an Adv Transp Infrastructure?

$14.1M across 55 payments, March 1, 2022 to July 24, 2026 — 4 purchase orders and 4 vendors, run by Transportation.

Checkbook LA · Through Sep 9, 2026

As published: ATSAC ENHANCE FOR AN ADV TRANSP INFRASTRUCTURE

Spans more than one contract

This budget line has run for 6 fiscal years across 4 separate purchase orders. A single payment in the register shows none of that — the commitment outlives any one order, and the orders are how it gets renewed.

$14.1MTotal spent
4Purchase orders
4Vendors
99%Largest vendor's share

Spending by fiscal year

FY2021-22
$4.6M
FY2022-23
$6.3M
FY2023-24
$2.3M
FY2024-25
$728K
FY2025-26
$68K
FY2026-27 *
$82K

* FY2026-27 is still in progress — not a full year. Same point of FY2025-26 (payments dated through Sep 9, 2025): $0.

Who was paid

Under which orders

20 payments · April 12, 2022 to March 13, 2024

30 payments · August 16, 2022 to July 24, 2026

1 payment · December 28, 2023 to December 28, 2023

4 payments · March 1, 2022 to March 1, 2022

Sources

LA Controller, Checkbook LA (pggv-e4fn), totalled nightly. Grouped by account_name, the budget line a payment is booked against — populated on every row, and the most useful field for understanding what a payment actually bought. Back to the checkbook.