What has the City paid on purchase order SC94MSACO17115226M?
$1.18M paid to Psomas /C across 54 payments from July 14, 2017 to August 3, 2022, charged to Transportation / Lincoln Bridge.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Coastal Transp Corridor Trust
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Transportation
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | July 14, 2017 | June 26, 2017 | 18d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $21,657 |
| 2 | July 14, 2017 | June 26, 2017 | 18d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $8,009 |
| 3 | July 14, 2017 | June 26, 2017 | 18d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $7,620 |
| 4 | July 14, 2017 | June 26, 2017 | 18d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $5,562 |
| 5 | July 14, 2017 | June 26, 2017 | 18d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $1,515 |
| 6 | August 31, 2017 | August 28, 2017 | 3d | LINCOLN BRIDGE MULTI-MODAL | $5,771 |
| 7 | December 4, 2017 | November 6, 2017 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $41,373 |
| 8 | December 4, 2017 | November 6, 2017 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $32,505 |
| 9 | December 4, 2017 | November 6, 2017 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $28,338 |
| 10 | December 4, 2017 | November 6, 2017 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $16,593 |
| 11 | December 4, 2017 | November 6, 2017 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $7,865 |
| 12 | March 28, 2018 | March 11, 2018 | 17d | LINCOLN BRIDGE MULTI-MODAL | $54,879 |
| 13 | March 28, 2018 | March 11, 2018 | 17d | LINCOLN BRIDGE MULTI-MODAL | $33,712 |
| 14 | March 28, 2018 | March 11, 2018 | 17d | LINCOLN BRIDGE MULTI-MODAL | $28,240 |
| 15 | March 28, 2018 | March 11, 2018 | 17d | LINCOLN BRIDGE MULTI-MODAL | $19,553 |
| 16 | March 28, 2018 | March 11, 2018 | 17d | LINCOLN BRIDGE MULTI-MODAL | $10,930 |
| 17 | August 14, 2018 | July 15, 2018 | 30d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $28,064 |
| 18 | August 29, 2018 | July 17, 2018 | 43d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $70,251 |
| 19 | August 29, 2018 | July 17, 2018 | 43d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $34,946 |
| 20 | August 29, 2018 | July 17, 2018 | 43d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $14,367 |
| 21 | August 29, 2018 | July 17, 2018 | 43d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $12,102 |
| 22 | November 15, 2018 | August 7, 2018 | 100d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $13,860 |
| 23 | November 15, 2018 | September 26, 2018 | 50d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $8,870 |
| 24 | March 14, 2019 | February 27, 2019 | 15d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $27,341 |
| 25 | April 25, 2019 | January 28, 2019 | 87d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $9,885 |
| 26 | April 25, 2019 | February 25, 2019 | 59d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $1,206 |
| 27 | June 7, 2019 | April 25, 2019 | 43d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $4,708 |
| 28 | October 24, 2019 | October 7, 2019 | 17d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $41,947 |
| 29 | October 24, 2019 | October 7, 2019 | 17d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $40,662 |
| 30 | October 24, 2019 | October 23, 2019 | 1d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $35,008 |
| 31 | October 24, 2019 | October 23, 2019 | 1d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $9,995 |
| 32 | October 25, 2019 | October 24, 2019 | 1d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $12,067 |
| 33 | November 4, 2019 | October 7, 2019 | 28d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $67,787 |
| 34 | January 28, 2020 | November 26, 2019 | 63d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $33,236 |
| 35 | January 28, 2020 | November 27, 2019 | 62d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $31,325 |
| 36 | January 28, 2020 | January 9, 2020 | 19d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $9,215 |
| 37 | February 25, 2020 | February 10, 2020 | 15d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $14,912 |
| 38 | March 13, 2020 | March 4, 2020 | 9d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $20,646 |
| 39 | April 14, 2020 | March 11, 2020 | 34d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $11,609 |
| 40 | June 22, 2020 | June 8, 2020 | 14d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $22,830 |
| 41 | June 22, 2020 | June 8, 2020 | 14d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $9,451 |
| 42 | June 23, 2020 | June 17, 2020 | 6d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $16,552 |
| 43 | June 23, 2020 | June 17, 2020 | 6d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $2,633 |
| 44 | October 14, 2020 | September 29, 2020 | 15d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $698 |
| 45 | October 19, 2020 | September 24, 2020 | 25d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $3,420 |
| 46 | December 18, 2020 | December 16, 2020 | 2d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $3,988 |
| 47 | April 6, 2021 | February 17, 2021 | 48d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $350 |
| 48 | May 13, 2021 | April 28, 2021 | 15d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $41,083 |
| 49 | May 13, 2021 | April 28, 2021 | 15d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $5,498 |
| 50 | May 21, 2021 | April 27, 2021 | 24d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1M | $2,155 |
| 51 | December 14, 2021 | December 7, 2021 | 7d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1,287,856.00 | $146,280 |
| 52 | April 20, 2022 | April 11, 2022 | 9d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1,287,856.00 | $24,014 |
| 53 | April 20, 2022 | April 11, 2022 | 9d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1,287,856.00 | $4,200 |
| 54 | August 3, 2022 | July 21, 2022 | 13d | LINCOLN BRIDGE MULTI-MODAL INCREASE TO $1,287,856.00 | $14,158 |