SpendingContractsPurchase order
What has the City paid on purchase order SC94CO22138550K?
$3.30M paid to Access Pacific Inc across 39 payments from June 16, 2022 to March 6, 2026, charged to Transportation / Boyle Heights Pedestrian Linkages-at New Sixth St Viaduct.
What it was for
Boyle Heights Pedestrian Linkages-at New Sixth St ViaductBudget line carrying the most money, of 2 this order is charged to.
Approval records
- Contract C-138550Stated in the order's descriptions.
Paid from
Transportation Grants Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Transportation
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | June 16, 2022 | May 17, 2022 | 30d | C-138550 PP#1 | $94,130 |
| 2 | July 26, 2022 | July 12, 2022 | 14d | C-138550 PP#2 | $82,887 |
| 3 | August 22, 2022 | August 3, 2022 | 19d | C-138550 PP#3 | $117,298 |
| 4 | October 12, 2022 | September 27, 2022 | 15d | C-138550 PP#4 | $91,033 |
| 5 | December 2, 2022 | October 31, 2022 | 32d | C-138550 PP#5 | $45,760 |
| 6 | December 21, 2022 | November 29, 2022 | 22d | C-138550 PP#6 | $136,770 |
| 7 | February 2, 2023 | January 6, 2023 | 27d | C-138550 PP#7 | $99,625 |
| 8 | February 28, 2023 | February 6, 2023 | 22d | C-138550 PP#8 | $139,602 |
| 9 | March 28, 2023 | March 1, 2023 | 27d | C-138550 PP#9 | $92,681 |
| 10 | April 13, 2023 | March 20, 2023 | 24d | C-138550 PP#10 | $163,092 |
| 11 | April 19, 2023 | April 10, 2023 | 9d | C-138550 PP#11 | $1,900 |
| 12 | June 9, 2023 | May 18, 2023 | 22d | C-138550 PP#12 | $100,209 |
| 13 | July 6, 2023 | June 22, 2023 | 14d | C-138550 PP#13 94NT73 | $133,344 |
| 14 | July 21, 2023 | June 22, 2023 | 29d | C-138550 PP#13 94NT73 CO#8-10 | $54,632 |
| 15 | August 16, 2023 | July 18, 2023 | 29d | C-138550 PP#14 | $114,563 |
| 16 | September 6, 2023 | August 24, 2023 | 13d | C-138550 PP#15 | $131,052 |
| 17 | November 2, 2023 | October 26, 2023 | 7d | C-138550 PP#16 | $110,936 |
| 18 | November 2, 2023 | October 26, 2023 | 7d | C-138550 PP#17 | $50,658 |
| 19 | November 20, 2023 | October 24, 2023 | 27d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $14,373 |
| 20 | November 20, 2023 | October 23, 2023 | 28d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $6,563 |
| 21 | December 28, 2023 | December 21, 2023 | 7d | C-138550 PP#18 | $49,566 |
| 22 | January 16, 2024 | November 30, 2023 | 47d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $5,730 |
| 23 | January 16, 2024 | November 30, 2023 | 47d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $692 |
| 24 | January 18, 2024 | December 29, 2023 | 20d | C-138550 PP#19 94NT73 | $149,426 |
| 25 | February 9, 2024 | January 11, 2024 | 29d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $9,735 |
| 26 | March 7, 2024 | February 9, 2024 | 27d | C-138550 PP#20 94NT73 | $125,758 |
| 27 | March 19, 2024 | March 5, 2024 | 14d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $8,132 |
| 28 | April 19, 2024 | March 22, 2024 | 28d | C-138550 PP#21 94NT73 | $58,002 |
| 29 | May 16, 2024 | April 26, 2024 | 20d | C-138550 PP#22 94NT73 | $210,233 |
| 30 | July 5, 2024 | June 14, 2024 | 21d | C-138550 PP#23 94NT73 | $64,437 |
| 31 | August 29, 2024 | August 9, 2024 | 20d | C-138550 PP#24 94NT73 | $44,586 |
| 32 | October 24, 2024 | October 22, 2024 | 2d | C-138550 PP#25 94NT73 | $41,330 |
| 33 | February 3, 2025 | January 7, 2025 | 27d | C-138550 PP#26 94NT73 | $39,135 |
| 34 | March 10, 2025 | February 14, 2025 | 24d | C-138550 PP#27 94NT73 | $134,888 |
| 35 | March 14, 2025 | January 29, 2025 | 44d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $90,328 |
| 36 | April 30, 2025 | April 9, 2025 | 21d | C-138550 PP#28 94NT73 | $273,505 |
| 37 | November 17, 2025 | November 5, 2025 | 12d | F59C/94YV63 ATP CYCLE 2: BOYLE HEIGHTS PED LINKAGES | $30,851 |
| 38 | November 21, 2025 | November 3, 2025 | 18d | C-138550 PP#29 94NT73 | $165,519 |
| 39 | March 6, 2026 | February 2, 2026 | 32d | C-138550 PP#30 94NT73 | $19,190 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.