SpendingContractsPurchase order
What has the City paid on purchase order SC94CO19128772M?
$2.95M paid to Ilium Associates Inc across 83 payments from August 16, 2018 to September 5, 2019, charged to Transportation / Marketing City Transit Program.
What it was for
Marketing City Transit Program
Budget line carrying the most money, of 7 this order is charged to.
Approval records
- Contract C-128772Award recorded in the City's procurement portal; see below.
Paid from
Transp Regulation &Enforcement
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Transportation
Awarded and paid so far
The City's procurement portal, RAMP, records contract C-128772 (the number embedded in this order's number, SC94CO19128772M) as awarded to Ilium Associates, Inc. for $32.3M (request for proposal), effective January 1, 2017 and expiring August 31, 2025. This order has paid $3.0M, 9% of that figure.
The award amount and dates are as entered in RAMP; later amendments that change a contract's ceiling or term are not always reflected there, and a contract can be paid through orders not shown on this page. RAMP title: “Transit Marketing - Customer Outreach and Support RFP”. See the award on RAMP
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | August 16, 2018 | July 17, 2018 | 30d | JUNE 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $98,992 |
| 2 | August 16, 2018 | July 18, 2018 | 29d | FY 2019 - TRANSTRACK - MAINTENANCE AND SUPPORT | $51,294 |
| 3 | September 12, 2018 | August 15, 2018 | 28d | JULY 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $180,384 |
| 4 | September 12, 2018 | August 15, 2018 | 28d | JULY 2018 - TRANSIT STORE - OPERATIONS | $53,690 |
| 5 | September 12, 2018 | August 15, 2018 | 28d | JULY 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 6 | September 12, 2018 | August 15, 2018 | 28d | JULY 2018 - DASH VERMONT AND MAIN REROUTE - LADOT TRANSIT MARKETING AND ADVERTISING | $1,951 |
| 7 | October 11, 2018 | September 13, 2018 | 28d | AUG 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $183,323 |
| 8 | October 11, 2018 | September 13, 2018 | 28d | AUG 2018 - TRANSIT STORE - OPERATIONS | $52,793 |
| 9 | October 11, 2018 | September 13, 2018 | 28d | AUG 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 10 | October 18, 2018 | September 20, 2018 | 28d | AUG 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $13,339 |
| 11 | October 18, 2018 | September 20, 2018 | 28d | AUG 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $3,191 |
| 12 | October 18, 2018 | September 20, 2018 | 28d | AUG 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 13 | October 31, 2018 | October 24, 2018 | 7d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,574 |
| 14 | October 31, 2018 | October 24, 2018 | 7d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,557 |
| 15 | November 13, 2018 | October 16, 2018 | 28d | SEP 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $163,502 |
| 16 | November 13, 2018 | October 16, 2018 | 28d | SEP 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 17 | November 14, 2018 | October 16, 2018 | 29d | SEP 2018 - TRANSIT STORE - OPERATIONS | $42,766 |
| 18 | November 15, 2018 | October 18, 2018 | 28d | JULY 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $32,089 |
| 19 | November 15, 2018 | October 18, 2018 | 28d | JULY 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $9,630 |
| 20 | November 15, 2018 | October 18, 2018 | 28d | SEP 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $5,903 |
| 21 | November 15, 2018 | October 18, 2018 | 28d | SEP 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 22 | November 15, 2018 | October 18, 2018 | 28d | JULY 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 23 | November 15, 2018 | October 18, 2018 | 28d | SEP 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $425 |
| 24 | November 27, 2018 | November 16, 2018 | 11d | MEASURE R_FUND 51Q_INCREASE $30,000 FY19 ENCUMBRANCE TO COVER BIKEWAYS AND VISION ZERO GIVEAWAYS. | $6,448 |
| 25 | November 28, 2018 | November 20, 2018 | 8d | NOV 2018 TECH MODE - LADOT TRANSIT MARKETING AND ADVERTISING | $50,000 |
| 26 | December 4, 2018 | November 6, 2018 | 28d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,585 |
| 27 | December 11, 2018 | November 13, 2018 | 28d | OCT 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $197,027 |
| 28 | December 11, 2018 | November 13, 2018 | 28d | OCT 2018 - TRANSIT STORE - OPERATIONS | $57,175 |
| 29 | December 11, 2018 | November 13, 2018 | 28d | OCT 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 30 | December 17, 2018 | November 19, 2018 | 28d | OCT 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $5,095 |
| 31 | December 17, 2018 | November 19, 2018 | 28d | OCT 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 32 | December 17, 2018 | November 19, 2018 | 28d | OCT 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $765 |
| 33 | January 3, 2019 | December 6, 2018 | 28d | NOV 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $154,694 |
| 34 | January 3, 2019 | December 6, 2018 | 28d | NOV 2018 - TRANSIT STORE - OPERATIONS | $43,231 |
| 35 | January 3, 2019 | December 6, 2018 | 28d | NOV 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 36 | January 15, 2019 | December 18, 2018 | 28d | NOV 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $13,334 |
| 37 | January 15, 2019 | December 18, 2018 | 28d | NOV 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $5,456 |
| 38 | January 15, 2019 | December 18, 2018 | 28d | NOV 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 39 | January 30, 2019 | January 4, 2019 | 26d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,491 |
| 40 | February 7, 2019 | January 11, 2019 | 27d | DEC 2018 - TRANSIT STORE - OPERATIONS | $41,422 |
| 41 | February 14, 2019 | January 18, 2019 | 27d | DEC 2018 - LADOT TRANSIT MARKETING AND ADVERTISING | $155,058 |
| 42 | February 14, 2019 | January 18, 2019 | 27d | DEC 2018 - REMIX - LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 43 | February 19, 2019 | January 22, 2019 | 28d | DEC 2018 - DASH - SIGN MAINTENANCE AND INSTALLATION | $4,759 |
| 44 | February 19, 2019 | January 22, 2019 | 28d | DEC 2018 - CE - SIGN MAINTENANCE AND INSTALLATION | $4,187 |
| 45 | February 19, 2019 | January 22, 2019 | 28d | DEC 2018 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 46 | March 14, 2019 | March 11, 2019 | 3d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,568 |
| 47 | March 19, 2019 | February 19, 2019 | 28d | JAN 2019 - LADOT TRANSIT MARKETING AND ADVERTISING | $194,984 |
| 48 | March 19, 2019 | February 19, 2019 | 28d | JAN 2019 - TRANSIT STORE - OPERATIONS | $48,465 |
| 49 | March 29, 2019 | March 1, 2019 | 28d | JAN 2019 - DASH - SIGN MAINTENANCE AND INSTALLATION | $4,381 |
| 50 | March 29, 2019 | March 1, 2019 | 28d | JAN 2019 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 51 | March 29, 2019 | March 1, 2019 | 28d | JAN 2019 - CE - SIGN MAINTENANCE AND INSTALLATION | $378 |
| 52 | April 9, 2019 | March 12, 2019 | 28d | FEB 2019 LADOT TRANSIT MARKETING AND ADVERTISING | $259,406 |
| 53 | April 9, 2019 | March 12, 2019 | 28d | FEB 2019 - TRANSIT STORE - OPERATIONS | $46,180 |
| 54 | April 9, 2019 | March 12, 2019 | 28d | FEB 2019 REMIX LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 55 | May 1, 2019 | April 3, 2019 | 28d | FEB 2019 - DASH - SIGN MAINTENANCE AND INSTALLATION | $12,408 |
| 56 | May 1, 2019 | April 3, 2019 | 28d | FEB 2019 - CE - SIGN MAINTENANCE AND INSTALLATION | $3,586 |
| 57 | May 1, 2019 | April 3, 2019 | 28d | FEB 2019 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 58 | May 9, 2019 | April 12, 2019 | 27d | MAR 2019 REMIX LADOT TRANSIT MARKETING AND ADVERTISING | $211,678 |
| 59 | May 9, 2019 | April 12, 2019 | 27d | MAR 2019 - TRANSIT STORE - OPERATIONS | $34,148 |
| 60 | May 22, 2019 | April 24, 2019 | 28d | MAR 2019 - CE - SIGN MAINTENANCE AND INSTALLATION | $26,287 |
| 61 | May 22, 2019 | April 24, 2019 | 28d | MAR 2019 - DASH - SIGN MAINTENANCE AND INSTALLATION | $6,272 |
| 62 | May 22, 2019 | April 24, 2019 | 28d | MAR 2019 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 63 | June 12, 2019 | May 15, 2019 | 28d | APR 2019 LADOT TRANSIT MARKETING AND ADVERTISING | $56,405 |
| 64 | June 12, 2019 | May 15, 2019 | 28d | APR 2019 - TRANSIT STORE - OPERATIONS | $40,525 |
| 65 | June 12, 2019 | May 16, 2019 | 27d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,629 |
| 66 | June 12, 2019 | May 16, 2019 | 27d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,568 |
| 67 | June 12, 2019 | May 16, 2019 | 27d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,568 |
| 68 | June 18, 2019 | May 21, 2019 | 28d | APR 2019 - CE - SIGN MAINTENANCE AND INSTALLATION | $10,112 |
| 69 | June 18, 2019 | May 21, 2019 | 28d | APR 2019 - DASH - SIGN MAINTENANCE AND INSTALLATION | $5,327 |
| 70 | June 18, 2019 | May 21, 2019 | 28d | APR 2019 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 71 | June 20, 2019 | June 5, 2019 | 15d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,539 |
| 72 | July 15, 2019 | July 2, 2019 | 13d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,586 |
| 73 | July 17, 2019 | July 16, 2019 | 1d | PRINTING & GRAPHICS FOR DOCKLESS PARKING ZONES | $22,950 |
| 74 | July 18, 2019 | June 21, 2019 | 27d | MAY 2019 LADOT TRANSIT MARKETING AND ADVERTISING | $174,519 |
| 75 | July 18, 2019 | June 21, 2019 | 27d | MAY 2019 - TRANSIT STORE - OPERATIONS | $51,600 |
| 76 | July 18, 2019 | June 21, 2019 | 27d | MAR 2019 REMIX LADOT TRANSIT MARKETING AND ADVERTISING | $7,000 |
| 77 | July 18, 2019 | June 21, 2019 | 27d | MAY 2019 REMIX LADOT TRANSIT MARKETING AND ADVERTISING | $6,167 |
| 78 | August 7, 2019 | July 26, 2019 | 12d | JUNE 2019 - DASH - SIGN MAINTENANCE AND INSTALLATION | $4,463 |
| 79 | August 7, 2019 | July 10, 2019 | 28d | JUNE 2019 - TRANSIT STORE - OPERATIONS | $2,602 |
| 80 | August 7, 2019 | July 26, 2019 | 12d | JUNE 2019 - WAY SINE - SIGN MAINTENANCE AND INSTALLATION | $990 |
| 81 | August 7, 2019 | July 26, 2019 | 12d | JUNE 2019 - CE - SIGN MAINTENANCE AND INSTALLATION | $378 |
| 82 | September 5, 2019 | August 22, 2019 | 14d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,557 |
| 83 | September 5, 2019 | August 22, 2019 | 14d | FY19 FOR THE MANAGEMENT OF THE TAXICABSLA.ORG WEBSITE & TAXICAB COMPLAINT HOTLINE | $2,555 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. Award from RAMP Opportunity Awards (h8mw-iegk), matched on the contract number embedded in this order's number and on the vendor's name. The City's biggest contracts · The checkbook.