What has the City paid on purchase order SC94CO18131121K?
$594K paid to 2 different vendors (the largest, John S Meek Company Inc, received $491.8K) across 11 payments from February 14, 2019 to September 27, 2021, charged to Transportation / Sunset Blvd Slope Mitigation - Coronado to Waterloo, Phase 1.
2 different vendors draw against this purchase order, so the $594K above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Measure M Local Return Special Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Transportation
Paid to
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | February 14, 2019 | January 29, 2019 | 16d | SUNSET BLVD SLOPE MITIGATION | $1,032 |
| 2 | February 21, 2019 | February 6, 2019 | 15d | SUNSET BLVD SLOPE MITIGATION | $159,130 |
| 3 | March 18, 2019 | March 12, 2019 | 6d | SUNSET BLVD SLOPE MITIGATION | $36,695 |
| 4 | April 9, 2019 | April 2, 2019 | 7d | SUNSET BLVD SLOPE MITIGATION | $124,621 |
| 5 | May 13, 2019 | May 6, 2019 | 7d | SUNSET BLVD SLOPE MITIGATION | $10,190 |
| 6 | June 12, 2019 | May 29, 2019 | 14d | SUNSET BLVD SLOPE MITIGATION | $5,690 |
| 7 | July 25, 2019 | July 5, 2019 | 20d | SUNSET BLVD SLOPE MITIGATION | $154,441 |
| 8 | March 18, 2021 | March 17, 2021 | 1d | SUNSET BLVD SLOPE MITIGATION - CORONADO TO WATERLOO PHASE 1 | $17,722 |
| 9 | May 18, 2021 | May 13, 2021 | 5d | SUNSET BLVD SLOPE MITIGATION - CORONADO TO WATERLOO PHASE 1-FINAL CLOSE-OUT CHANGE ORDER | $78,061 |
| 10 | September 27, 2021 | July 23, 2021 | 66d | SUNSET BLVD SLOPE MITIGATION - CORONADO TO WATERLOO PHASE 1 | $6,347 |
| 11 | September 27, 2021 | July 23, 2021 | 66d | SUNSET BLVD SLOPE MITIGATION - CORONADO TO WATERLOO PHASE 1 | $103 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.