SpendingContractsPurchase order

What has the City paid on purchase order SC94CO18128491M?

$42K paid to J. L. Moody Construction & Development, Inc. across 4 payments from June 14, 2018 to January 30, 2019, charged to Transportation / Sidewalk Repair Contractual Services.

What it was for

Sidewalk Repair Contractual Services

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Local Transportation

a capital fund, typically bond or grant financed rather than annual tax revenue.

Department: Transportation

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1June 14, 2018June 8, 20186dSIDEWALK REPAIR PROGRAM-SMALL SIDEWALK WORK PACKAGE #14(W.O. NO. E1908365)$19,411
2August 22, 2018August 7, 201815dINCREASE $15,930.68 PER CHANGE ORDER NO. 001 AND THE NEW CONTRACT COMPLETION DATE IS 9/18/2018.$15,134
3January 15, 2019January 4, 201911dDECREASE $30,336.90 PER FINAL CLOSE OUT CHANGE ORDER.$1,502
4January 30, 2019January 15, 201915dADDED $30 DUE TO DECREASE OF $30,336.90 WAS CALCULATED SHORT.$5,814

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.