What has the City paid on purchase order SC94CO18127166M?

$694K paid to Alexandra Rudoff across 23 payments from August 3, 2017 to May 9, 2024, charged to Transportation / Traffic Asset Management System.

What it was for

Traffic Asset Management System

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Proposition C Antigridlock Imp

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Transportation

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 3, 2017July 10, 201724dE002 FUND 49C MEMBERSHIP$25,000
2August 3, 2017July 10, 201724dE002 CREATE TGFUND PROJECT FINANCE MANAGEMENT SYSTEM$14,583
3August 4, 2017July 10, 201725dE002 UPGRADE EXISTING EWORKS$20,000
4August 4, 2017July 10, 201725dE002 UPGRADE EXISTING MYLADOT$17,500
5October 4, 2017September 22, 201712dE002 FUND 49C USER INTERFACE$40,000
6January 29, 2018January 23, 20186dE002 TEMPORARY PREFERENTIAL PARKING DISTRICT SYSTEM$32,500
7February 8, 2018January 23, 201816dE002 UPGRADE EXISTING MYLADOT AND EWORKS$10,000
8February 8, 2018January 23, 201816dE002 UPGRADE EXISTING MYLADOT AND EWORKS$5,250
9April 6, 2018April 2, 20184dE002 TEMPORARY PREFERENTIAL PARKING DISTRICT SYSTEM$76,250
10June 5, 2018May 25, 201811dE002 TEMPORARY PREFERENTIAL PARKING DISTRICT SYSTEM$28,125
11July 18, 2018June 29, 201819dE002 TEMPORARY PREFERENTIAL PARKING DISTRICT SYSTEM$40,625
12December 19, 2018November 20, 201829dE002 TEMPORARY PREFERENTIAL PARKING DISTRICT SYSTEM$7,500
13March 18, 2019February 28, 201918dE002 UPGRADE EXISTING MYLADOT AND EWORKS$88,000
14July 24, 2019July 15, 20199dE002 UPGRADE EXISTING MYLADOT AND EWORKS$62,750
15January 2, 2020December 19, 201914dE002 CREATE TGFUND PROJECT FINANCE MANAGEMENT SYSTEM$53,958
16January 7, 2020December 14, 201924dE002 UPGRADE EXISTING MYLADOT AND EWORKS$13,250
17March 8, 2021February 26, 202110dE002 UPGRADE EXISTING MYLADOT AND EWORKS$12,250
18March 8, 2021February 22, 202114dE002 UPGRADE EXISTING MYLADOT AND EWORKS$6,000
19June 9, 2022May 19, 202221dE002 UPGRADE EXISTING MYLADOT AND EWORKS$7,000
20September 28, 2022September 2, 202226dE002 UPGRADE EXISTING MYLADOT AND EWORKS$42,000
21January 18, 2023January 11, 20237dE002 UPGRADE EXISTING MYLADOT AND EWORKS$63,000
22July 5, 2023June 30, 20235dE002 UPGRADE EXISTING MYLADOT AND EWORKS$11,200
23May 9, 2024May 1, 20248dE002 UPGRADE EXISTING MYLADOT AND EWORKS$16,800

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.