SpendingContractsPurchase order

What has the City paid on purchase order SC94CO18123910K?

$1.39M paid to 2 different vendors (the largest, John S Meek Company Inc, received $1.4M) across 21 payments from August 2, 2018 to November 4, 2019, charged to Transportation / Davies Way (2044) Bulkhead.

A blanket order, not one firm's contract

2 different vendors draw against this purchase order, so the $1.4M above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

Davies Way (2044) Bulkhead

Budget line carrying the most money, of 4 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Measure M Local Return Special Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Transportation

Paid to

John S Meek Company Inc$1.4M · 20 payments

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 2, 2018July 24, 20189dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$105,532
2August 13, 2018August 7, 20186dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$73,607
3August 28, 2018August 13, 201815dEUCALYPTUS LANE (6006) BULKHEAD GEOTECH/STRUCTURAL SVCS$147,183
4August 28, 2018August 21, 20187dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$120,792
5October 10, 2018October 2, 20188dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$19,403
6October 18, 2018September 19, 201829dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$220,911
7October 31, 2018October 17, 201814dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$46,473
8December 20, 2018December 3, 201817dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$1,034
9December 21, 2018November 27, 201824dCASTELLAMMARE DR (17434) BULKHEAD & SEWER GEOTECH/STRUCT SVC$285,358
10February 6, 2019January 15, 2018387dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$36,841
11February 6, 2019January 16, 201921dEUCALYPTUS LANE (6006) BULKHEAD GEOTECH/STRUCTURAL SVCS$13,903
12February 6, 2019January 24, 201913dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$6,789
13February 20, 2019February 8, 201912dEUCALYPTUS LANE (6006) BULKHEAD GEOTECH/STRUCTURAL SVCS$7,584
14March 7, 2019February 21, 201914dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$22,993
15March 28, 2019March 12, 201916dCASTELLAMMARE DR (17434) BULKHEAD & SEWER GEOTECH/STRUCT SVC$25,093
16April 25, 2019April 17, 20198dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$43,758
17April 26, 2019April 19, 20197dCAZADOR STREET BULKHEAD (E1907781) GEOTECH/STRUCTURAL SVCS$8,100
18June 21, 2019May 31, 201921dCASTELLAMMARE DR (17434) BULKHEAD & SEWER GEOTECH/STRUCT SVC$142,630
19July 11, 2019June 12, 201929dDAVIES WAY (2044) BULKHEAD GEOTECH/STRUCTURAL SVCS$24,483
20August 19, 2019August 2, 201917dEUCALYPTUS LANE (6006) BULKHEAD GEOTECH/STRUCTURAL SVCS$23,896
21November 4, 2019October 11, 201924dCASTELLAMMARE DR (17434) BULKHEAD & SEWER GEOTECH/STRUCT SVC$17,271

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.