What has the City paid on purchase order SC89CO21003738K?

$1.09M paid to Commercial Coating Co Inc across 36 payments from August 12, 2020 to July 29, 2022, charged to Recreation and Parks - Special Accounts / Quimby in Lieu Fee.

What it was for

Quimby in Lieu Fee

Budget line carrying the most money, of 8 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Recreation and Parks

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Recreation and Parks - Special Accounts

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 12, 2020August 6, 20206d#21009 302/89460K-HO HOLMBY PARK -WALKWAY REPAIR, INV#2007054 DTD 07/22/20 $68,500$68,500
2August 31, 2020August 27, 20204dQP000784 #21350 302/89718H HERMON PARK-TENNIS COURT PATH OF TRAVEL, INV#2008052 DTD 08/25/20 $35,000$35,000
3September 1, 2020August 31, 20201d#21325 205/89SRGN ALLEGHENY PARK-BUILDING DEMOLITION, INV#2007063 DTD 07/24/20 $131,415$131,415
4September 1, 2020August 31, 20201d#21325 205/89SRGN ALLEGHENY PARK-BUILDING DEMOLITION, INV#2007064 DTD 07/24/20 $11,302$11,302
5September 1, 2020August 31, 20201d#21325 205/89SRGN ALLEGHENY PARK-BUILDING DEMOLITION, INV#2007065 DTD 07/24/20 $8,832$8,832
6September 15, 2020September 3, 202012dGRIFFITH PARK GC -COMM PAVING & COATING CO003738 NTP 8/19/20$28,500
7September 21, 2020September 17, 20204dQT074684 #21256 302/89716H EAGLE ROCK PARK, INV# 2009031 DTD 09/16/20 $57,734.38$57,734
8September 21, 2020September 17, 20204dQT073755 #21256 302/89716H EAGLE ROCK PARK, INV# 2009031 DTD 09/16/20 $17,265.62$17,266
9September 23, 2020September 22, 20201dQP000784 #21350 302/89718H HERMON PARK-TENNIS COURT PATH OF TRAVEL, INV#2009034 DTD 09/17/20 $2,500$2,500
10September 29, 2020September 28, 20201d#21376 302/89SRGQ LINCOLN HEIGHTS RC-TOPOGRAPHIC SURVEY, INV#2009047 DTD 09/24/20 $18,450$18,450
11October 6, 2020October 5, 20201d#21254 205/89SRGO BROOKLYN HEIGHTS PARK-BUILDING DEMOLITION, INV#2009059 DTD 09/30/20 $11,426.40$11,426
12October 6, 2020October 5, 20201d#21254 205/89SRGO BROOKLYN HEIGHTS PARK-BUILDING DEMOLITION, INV#2009060 DTD 09/30/20 $8,500$8,500
13October 7, 2020October 5, 20202d#21254 205/89SRGO BROOKLYN HEIGHTS PARK-BUILDING DEMOLITION, INV#2009058 DTD 09/30/20 $107,975$107,975
14October 28, 2020October 19, 20209dQT082584 #21411 302/89716H ALLEGHENY PARK, INV#2010021 DTD 10/14/20 $14,364.36$14,364
15October 28, 2020October 19, 20209dQP001375 #21411 302/89718H ALLEGHENY PARK, INV#2010021 DTD 10/14/20 $6,935.64$6,936
16November 16, 2020November 10, 20206dQT074684 #21256 302/89716H EAGLE ROCK PARK, INV#2010052 DTD 10/30/20 $33,500$33,500
17November 16, 2020November 10, 20206dQT073755 #21256 302/89716H EAGLE ROCK PARK-TENNIS COURT PATH, INV#2010053 DTD 10/30/20 $1,750$1,750
18January 7, 2021January 5, 20212dGRIFFITH PARK GC -COMM PAVING & COATING CO003738 NTP 11/24/20$62,500
19January 7, 2021January 5, 20212dGRIFFITH PARK GC -COMM PAVING & COATING CO003738 NTP 11/24/20$17,500
20February 2, 2021February 2, 20210d#21254 205/89SRGO BROOKLYN HEIGHTS PARK-BUILDING DEMOLITION, INV#2010001 DTD 10/05/20 $12,655$12,655
21March 9, 2021March 2, 20217d#21325 205/89SRGN ALLEGHENY PARK-BUILDING DEMOLITION, INV#2102037 DTD 02/24/21 $36,280$36,280
22March 9, 2021March 1, 20218d#20398 302/89460K-LK WEST LAKESIDE STREET PARK, INV#2102033 DTD 02/24/21 $8,500$8,500
23May 11, 2021May 10, 20211dQT073929 #21471 302/89716H ECHO PARK-PARKING LOT REF & REPAIR, INV#2105005 DTD 05/05/21 $20,250$20,250
24June 9, 2021June 7, 20212dGRIFFITH PARK GC -COMM PAVING & COATING CO003738 NTP 11/24/20$15,000
25June 21, 2021June 16, 20215dWEST OBSERVATORY ROAD - STRIPING AND PAINT PROJECT NTP 2/9/21 FINAL$26,500
26August 18, 2021August 11, 20217dQT067577 #21372 302/89716H GRIFFITH PARK BOYS CAMP,INV#2105002 DTD 05/05/21 $18,000$18,000
27August 23, 2021August 20, 20213dQT069297 #21372 302/89716H GRIFFITH PARK BOYS CAMP, INV# 2108043 DTD 08/19/21 $35,000.00$23,299
28August 23, 2021August 20, 20213dQT067577 #21372 302/89716H GRIFFITH PARK BOYS CAMP, INV# 2108043 DTD 08/19/21 $35,000.00$11,701
29September 1, 2021August 31, 20211dQT073790 #21456 302/89716H DEL REY LAGOON - NW PARKING LOT, INV# 2108067 DTD 08/30/21 $15,000.00$15,000
30October 4, 2021September 21, 202113dQT067577 #21372 302/89716H GRIFFITH PARK BOYS CAMP, INV#2109054 DTD 09/20/21 $29,500.00$29,500
31March 9, 2022March 3, 20226dQT073790 #21456 302/89716H DEL REY LAGOON, INV# 2203003 DTD 03/01/22 $50,000.00$50,000
32July 29, 2022July 20, 20229dQP001183 #21456 302/89718H DEL REY LAGOON, INV# 2206030 DTD 06/17/22 $184,150.00$110,225
33July 29, 2022July 20, 20229dQT074017 #21456 302/89716H DEL REY LAGOON, INV# 2206030 DTD 06/17/22 $184,150.00$21,053
34July 29, 2022July 20, 20229dQM170494 #21456 302/89716H DEL REY LAGOON, INV# 2206030 DTD 06/17/22 $184,150.00$19,644
35July 29, 2022July 20, 20229dQP000055 #21456 302/89718H DEL REY LAGOON, INV# 2206030 DTD 06/17/22 $184,150.00$18,407
36July 29, 2022July 20, 20229dQT073790 #21456 302/89716H DEL REY LAGOON, INV# 2206030 DTD 06/17/22 $184,150.00$7,171

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.