SpendingContractsPurchase order

What has the City paid on purchase order SC89CO19124705M?

$310K paid to Rios Clementi Hale Studios across 18 payments from August 29, 2018 to October 20, 2020, charged to Recreation and Parks - Special Accounts / Greek Theatre Capital Improvements.

What it was for

Greek Theatre Capital Improvements

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Greek Theatre Special Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Recreation and Parks - Special Accounts

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 29, 2018August 7, 201822dGREEK THEATER FACILITY ENHANCEMENT NTP#11-ADD#19$5,130
2August 29, 2018August 6, 201823dGREEK THEATER FACILITY ENHANCEMENT NTP#7-TOS14$1,667
3December 18, 2018December 10, 20188dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4) SEP18$31,944
4December 18, 2018December 10, 20188dGREEK THEATER FACILITY ENHANCEMENT NTP#12 (PHASE 4) JUNE18$11,760
5December 18, 2018December 10, 20188dGREEK THEATER FACILITY ENHANCEMENT NTP#12 (PHASE 4) AUG18$8,400
6December 18, 2018December 10, 20188dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4) AUG18$6,499
7December 18, 2018December 10, 20188dGREEK THEATER FACILITY ENHANCEMENT NTP#12 (PHASE 4) SEP18$4,547
8June 4, 2019June 3, 20191dGREEK THEATER FACILITY ENHANCEMENT NTP#13 - ADD#21$88,197
9June 5, 2019June 3, 20192dGREEK THEATER FACILITY ENHANCEMENT NTP#12 - ADD#20$30,392
10December 18, 2019December 17, 20191dGREEK THEATER FACILITY ENHANCEMENT NTP#14 (PHASE 4)$20,400
11December 18, 2019December 17, 20191dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$17,864
12December 18, 2019December 17, 20191dGREEK THEATER FACILITY ENHANCEMENT NTP#12 (PHASE 4)$15,566
13March 16, 2020February 19, 202026dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$39,269
14April 9, 2020March 16, 202024dGREEK THEATER FACILITY ENHANCEMENT NTP#14 (PHASE 4)$1,800
15April 9, 2020March 16, 202024dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$1,080
16October 20, 2020September 22, 202028dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$12,131
17October 20, 2020September 22, 202028dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$11,194
18October 20, 2020September 22, 202028dGREEK THEATER FACILITY ENHANCEMENT NTP#13 (PHASE 4)$1,716

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.