What has the City paid on purchase order SC88CO19003647K?

$1.23M paid to Electro Construction Corp across 22 payments from October 5, 2018 to December 4, 2020, charged to Recreation and Parks / Griffith Observatory-Imp.

What it was for

Griffith Observatory-Imp

Budget line carrying the most money, of 7 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Recreation and Parks

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Recreation and Parks

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1October 5, 2018September 12, 201823d#21164. ECHO PARK TENNIS COURTS - INSTALLATION OF SECURITY CAMERA CO#3 7/17/18$10,481
2October 9, 2018September 12, 201827d#21094 205/88MMD3 HARBOR HIGHLANDS PK, INV# 1737-3 DTD 8/20/18 $4,509$4,509
3November 20, 2018October 29, 201822d#21164. ECHO PARK TENNIS COURTS - INSTALL OF SECURITY CAMERA CO#4 9/20/18$2,629
4April 30, 2019April 4, 201926dTOBERMAN RC - POLE REPLACEMENT NTP 2/5/19.$2,661
5May 14, 2019April 22, 201922d#21244 205/88170J GRIFFITH OBSERVATORY - LIGHTING IMPR INV# 1863-2 $315,900.00$315,900
6June 13, 2019June 3, 201910d#21244 205/88170J GRIFFITH OBSERVATORY - LIGHTING IMPR INV# 1836-3 $296,944.90 OF $533,064.00$296,945
7June 13, 2019June 3, 201910d#21244 205/88130L GRIFFITH OBSERVATORY - LIGHTING IMPR INV# 1836-3 $34,166.15 OF $534,064.00$34,166
8July 26, 2019July 2, 201924d#20814. BISHOP CANYON BALLFIELD IMPROVEMENTS - ELECTRICAL CO#4. NTP 5/2/19. PP#1$12,461
9September 16, 2019September 6, 201910d#20789 209/88K303 HAZARD PARK, INV# 1924-1 DTD 7/26/19 $109,429$109,429
10October 11, 2019October 8, 20193d#21192 205/88NQAW CSY EMERGENCY OPERATION CENTER, INV#1939-1 R.1 DTD 10/04/19 $105,304$105,304
11November 7, 2019October 10, 201928dBISHOP CANYON BALLFIELD IMPROVEMENTS - ELECTRICAL CO#4 5/2/19$255
12November 12, 2019October 18, 201925dDEVONSHIRE POLICE STATION - ELECTRICAL AND IRRIGATION CONTROL INSTALLATION NTP 5/16/19$11,463
13November 15, 2019October 22, 201924dHOOVER GAGE PARK - ELECTRICAL SERVICE EQUIPMENT REPLACEMENT AND LIGHTING UPGRADE NTP 5/21/19$32,235
14December 5, 2019December 3, 20192d#20789 209/88K303 HAZARD PARK-CCTV & LIGHTING IMPROVEMENT, INV#1924-2 DTD 10/17/19 $40,475$40,475
15December 11, 2019December 3, 20198d#21076 205/88LD27 ELYSIAN PARK GREENBELT-BOOSTER PUMP POWER, INV#1918-1 DTD 10/17/19 $15,335$15,335
16February 4, 2020January 30, 20205d#21076 205/88LD27 ELYSIAN PARK GREENBELT-BOOSTER PUMP POWER, INV#1918-2 DTD 1/29/20 $1,704$1,704
17March 19, 2020February 24, 202024dHOOVER GAGE PARK - ELECTRICAL SERVICE EQUIPMENT REPLACEMENT & LIGHTING UPGRADE NTP 5/21/19. FINAL$1,697
18May 27, 2020May 19, 20208d#21192 205/88NQAW CSY EMERGENCY OPERATION CENTER, INV#1939-2 DTD 04/30/20 $40,502.30$40,502
19August 3, 2020July 30, 20204d#21192 205/88NQAW CSY EMERGENCY OPERATION CENTER, INV#1939-3 DTD 06/26/20 $16,200.70$16,201
20August 27, 2020August 10, 202017dVALLEY PLAZA RC - ELECTRIC SERVICE EQUIPMENT REPLACEMENT NTP 5/8/19$24,247
21August 28, 2020August 11, 202017dANGEL'S GATE PARK CENTER - POLES RESTORATION 6/18/19 PP#1 CO#6 (PP)$90,262
22December 4, 2020November 10, 202024dANGEL'S GATE PARK CENTER - POLES RESTORATION CO#6 6/18/19 FINAL$63,677

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.