SpendingContractsPurchase order
What has the City paid on purchase order SC86CO24144960M?
$671K paid to 2 different vendors (the largest, Far East Landscape and Maintenance,, received $427.4K) across 17 payments from April 15, 2024 to July 10, 2025, charged to Public Works - Street Services / Contractual Services.
2 different vendors draw against this purchase order, so the $671K above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.
What it was for
Contractual Services
Budget line.
Order description, as published:
ENCUMBER $670,649.78 FOR FY23-24 LANDSCAPE MAINT- WEST VALLE
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated February 28, 2024.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: Public Works - Street Services
Paid to
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | April 15, 2024 | March 14, 2024 | 32d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $27,866 |
| 2 | May 24, 2024 | April 9, 2024 | 45d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $34,186 |
| 3 | July 25, 2024 | May 6, 2024 | 80d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $45,102 |
| 4 | July 25, 2024 | June 21, 2024 | 34d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $44,697 |
| 5 | August 19, 2024 | July 1, 2024 | 49d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $46,430 |
| 6 | September 9, 2024 | August 1, 2024 | 39d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $37,193 |
| 7 | September 9, 2024 | August 1, 2024 | 39d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $7,748 |
| 8 | November 14, 2024 | August 26, 2024 | 80d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $43,320 |
| 9 | December 18, 2024 | October 26, 2024 | 53d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $51,588 |
| 10 | December 18, 2024 | October 26, 2024 | 53d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $49,894 |
| 11 | March 4, 2025 | December 2, 2024 | 92d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $51,588 |
| 12 | March 6, 2025 | December 26, 2024 | 70d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $51,588 |
| 13 | March 6, 2025 | January 31, 2025 | 34d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $51,588 |
| 14 | March 17, 2025 | February 4, 2025 | 41d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $13,570 |
| 15 | April 16, 2025 | March 12, 2025 | 35d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $33,532 |
| 16 | May 15, 2025 | April 7, 2025 | 38d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $46,430 |
| 17 | July 10, 2025 | April 30, 2025 | 71d | LANDSCAPE MAINTENANCE OF MEDIAN ISLANDS-WEST VALLEY | $34,328 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.