SpendingContractsPurchase order
What has the City paid on purchase order SC82CO23141551M?
$171K paid to Allied Protection Services Inc across 23 payments from January 19, 2023 to August 11, 2023, charged to Public Works - Sanitation / Contractual Services.
What it was for
Contractual Services
Budget line.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: Public Works - Sanitation
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | January 19, 2023 | December 7, 2022 | 43d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,647 |
| 2 | January 20, 2023 | December 7, 2022 | 44d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,382 |
| 3 | January 20, 2023 | December 7, 2022 | 44d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,647 |
| 4 | January 25, 2023 | January 3, 2023 | 22d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,911 |
| 5 | January 25, 2023 | January 3, 2023 | 22d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,823 |
| 6 | January 25, 2023 | January 3, 2023 | 22d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,794 |
| 7 | February 28, 2023 | February 21, 2023 | 7d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,919 |
| 8 | March 3, 2023 | February 21, 2023 | 10d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $7,073 |
| 9 | March 3, 2023 | February 21, 2023 | 10d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,573 |
| 10 | March 7, 2023 | February 21, 2023 | 14d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,352 |
| 11 | March 13, 2023 | February 21, 2023 | 20d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,661 |
| 12 | March 13, 2023 | February 21, 2023 | 20d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,661 |
| 13 | March 29, 2023 | March 8, 2023 | 21d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $6,617 |
| 14 | April 17, 2023 | March 30, 2023 | 18d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,647 |
| 15 | May 18, 2023 | April 5, 2023 | 43d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,588 |
| 16 | May 26, 2023 | May 4, 2023 | 22d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,676 |
| 17 | June 16, 2023 | May 18, 2023 | 29d | SECURITY SERVICES FOR SOUTH COLLECTION YARD-NORTH CENTRAL | $18,087 |
| 18 | June 16, 2023 | May 10, 2023 | 37d | SECURITY SERVICES FOR SOUTH COLLECTION YARD-NORTH CENTRAL | $17,518 |
| 19 | June 16, 2023 | May 17, 2023 | 30d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,882 |
| 20 | June 21, 2023 | May 17, 2023 | 35d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,669 |
| 21 | August 8, 2023 | July 1, 2023 | 38d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $5,411 |
| 22 | August 11, 2023 | July 26, 2023 | 16d | SECURITY SERVICES FOR SOUTH COLLECTION YARD-NORTH CENTRAL | $12,964 |
| 23 | August 11, 2023 | July 26, 2023 | 16d | SECURITY SERVICES AT EAST & WEST VALLEY SANITATION YARD | $4,794 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.