SpendingContractsPurchase order
What has the City paid on purchase order SC74CO24136591M?
$1.28M paid to West Valley Alliance /C across 36 payments from August 25, 2023 to July 31, 2024, charged to Public Works - Board of Public Works / Contractual Services.
What it was for
Contractual Services
Budget line.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: Public Works - Board of Public Works
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | August 25, 2023 | August 15, 2023 | 10d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 2 | August 25, 2023 | August 15, 2023 | 10d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 3 | August 25, 2023 | August 15, 2023 | 10d | CLEAN STREETS LA SERVICES | $2,146 |
| 4 | September 14, 2023 | September 5, 2023 | 9d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 5 | September 26, 2023 | September 5, 2023 | 21d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 6 | September 26, 2023 | September 5, 2023 | 21d | CLEAN STREETS LA SERVICES | $2,146 |
| 7 | October 19, 2023 | October 2, 2023 | 17d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 8 | October 19, 2023 | October 2, 2023 | 17d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 9 | October 31, 2023 | October 2, 2023 | 29d | CLEAN STREETS LA SERVICES | $2,146 |
| 10 | November 21, 2023 | November 2, 2023 | 19d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 11 | November 21, 2023 | November 2, 2023 | 19d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 12 | November 21, 2023 | November 2, 2023 | 19d | CLEAN STREETS LA SERVICES | $2,146 |
| 13 | December 26, 2023 | December 4, 2023 | 22d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 14 | December 26, 2023 | December 4, 2023 | 22d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 15 | December 26, 2023 | December 4, 2023 | 22d | CLEAN STREETS LA SERVICES | $2,146 |
| 16 | January 18, 2024 | January 3, 2024 | 15d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 17 | January 22, 2024 | January 3, 2024 | 19d | CLEAN STREETS LA SERVICES | $8,935 |
| 18 | January 25, 2024 | January 3, 2024 | 22d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 19 | February 14, 2024 | February 1, 2024 | 13d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 20 | February 14, 2024 | February 1, 2024 | 13d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 21 | February 22, 2024 | February 1, 2024 | 21d | CLEAN STREETS LA SERVICES | $6,086 |
| 22 | March 19, 2024 | March 1, 2024 | 18d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 23 | March 27, 2024 | March 1, 2024 | 26d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 24 | March 27, 2024 | March 1, 2024 | 26d | CSLA PUBLIC RIGHT-OF-WAY CLEANUP DURING FISCAL YEAR 2023-24 | $5,150 |
| 25 | April 17, 2024 | April 2, 2024 | 15d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 26 | April 17, 2024 | April 2, 2024 | 15d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 27 | April 17, 2024 | April 5, 2024 | 12d | CSLA PUBLIC RIGHT-OF-WAY CLEANUP DURING FISCAL YEAR 2023-24 | $5,150 |
| 28 | May 13, 2024 | April 30, 2024 | 13d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 29 | May 13, 2024 | April 30, 2024 | 13d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 30 | May 13, 2024 | April 30, 2024 | 13d | CSLA PUBLIC RIGHT-OF-WAY CLEANUP DURING FISCAL YEAR 2023-24 | $5,150 |
| 31 | June 10, 2024 | June 2, 2024 | 8d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 32 | June 10, 2024 | June 2, 2024 | 8d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 33 | June 10, 2024 | June 2, 2024 | 8d | CSLA PUBLIC RIGHT-OF-WAY CLEANUP DURING FISCAL YEAR 2023-24 | $5,150 |
| 34 | July 31, 2024 | July 3, 2024 | 28d | GRAFFITI REMOVAL SERVICES FOR FY23-24 | $87,500 |
| 35 | July 31, 2024 | July 3, 2024 | 28d | SUPPLEMENTAL CLEANUP SERVICES IN CD 12 | $15,000 |
| 36 | July 31, 2024 | July 3, 2024 | 28d | CSLA PUBLIC RIGHT-OF-WAY CLEANUP DURING FISCAL YEAR 2023-24 | $5,150 |
Download this table: ·
Draw-down shape
Sources