What has the City paid on purchase order SC68MSACO17129412M?

$275K paid to Dudek across 27 payments from September 19, 2017 to June 10, 2020, charged to City Planning / Contractual Services.

What it was for

Contractual Services

Budget line.

Approval records

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: City Planning

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1September 19, 2017August 24, 201726dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$3,646
2September 21, 2017August 25, 201727dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$7,138
3October 10, 2017September 14, 201726dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$4,223
4November 17, 2017October 25, 201723dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$2,260
5December 14, 2017November 20, 201724dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$10,473
6January 23, 2018December 28, 201726dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$10,360
7February 15, 2018January 23, 201823dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$25,325
8March 21, 2018February 26, 201823dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$1,300
9May 1, 2018April 5, 201826dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$42,045
10May 23, 2018April 30, 201823dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$11,146
11May 23, 2018April 30, 201823dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF16-0999 (F434)$8,785
12June 25, 2018June 13, 201812dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$19,607
13September 17, 2018August 22, 201826dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$62,442
14September 17, 2018August 22, 201826dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$4,570
15October 12, 2018September 18, 201824dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$5,063
16November 16, 2018October 24, 201823dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$21,420
17November 28, 2018November 4, 201824dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$220
18February 12, 2019January 17, 201926dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$80
19November 22, 2019October 30, 201923dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$110
20December 10, 2019November 21, 201919dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$708
21February 21, 2020January 28, 202024dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$510
22February 21, 2020January 28, 202024dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$220
23February 25, 2020January 31, 202025dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$5,828
24April 3, 2020March 10, 202024dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$5,843
25May 19, 2020April 24, 202025dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$11,570
26May 19, 2020April 24, 202025dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$7,370
27June 10, 2020June 5, 20205dVENICE LCP (PHASE II)-SEA LEVEL RISE & CLIMATE CHANGE, CF12-1944-S5 (F434)$3,115

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.