SpendingContractsPurchase order

What has the City paid on purchase order SC68CO25144481M?

$1.25M paid to Commercial Programming Systems Inc across 74 payments from August 5, 2024 to August 12, 2025, charged to City Planning / Contractual Services.

What it was for

Contractual Services

Budget line.

Order description, as published:

ENCUMBRANCE FOR COMMERCIAL PROGRAMMING SYSTEMS, INC

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated July 16, 2024.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: City Planning

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 5, 2024July 12, 202424d(F588)VARIOUS DEPT PROJECTS- GABRIEL BARGA & JASON BYORS$5,338
2August 22, 2024August 19, 20243d(F588)GIS DATABASE MAINTENANCE- EVAN BAGHERI & NIA BEAZER$11,254
3August 22, 2024August 19, 20243d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$10,000
4September 4, 2024August 23, 202412d(F588)VARIOUS DEPT PROJECTS-GABRIEL, JASON, GLORIA, & CRAIG$31,608
5September 4, 2024August 23, 202412d(F588)VARIOUS DEPT PROJECTS-GABRIEL, JASON, GLORIA, & CRAIG$18,052
6September 4, 2024August 23, 202412d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$16,720
7October 4, 2024September 10, 202424d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$12,500
8October 17, 2024October 8, 20249d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,728
9October 17, 2024October 8, 20249d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,342
10October 22, 2024October 9, 202413d(F588)VARIOUS DEPT PROJECTS$51,283
11October 22, 2024October 9, 202413d(F588)VARIOUS DEPT PROJECTS$19,757
12October 29, 2024October 3, 202426d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$22,000
13October 29, 2024October 3, 202426d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$9,467
14October 29, 2024October 3, 202426d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$9,419
15November 1, 2024October 8, 202424d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$10,000
16November 15, 2024October 22, 202424d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$16,720
17December 6, 2024November 12, 202424d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$10,000
18December 9, 2024November 14, 202425d(F588)VARIOUS DEPT PROJECTS$31,608
19December 9, 2024November 14, 202425d(F588)VARIOUS DEPT PROJECTS$17,993
20December 10, 2024November 14, 202426d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$17,600
21December 24, 2024December 2, 202422d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,342
22December 24, 2024December 2, 202422d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,293
23January 3, 2025December 19, 202415d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$19,360
24January 3, 2025December 19, 202415d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$15,750
25January 3, 2025December 19, 202415d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$8,646
26January 3, 2025December 19, 202415d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$8,597
27January 7, 2025December 19, 202419d(F588)VARIOUS DEPT PROJECTS$36,599
28January 7, 2025December 19, 202419d(F588)VARIOUS DEPT PROJECTS$21,168
29February 10, 2025January 21, 202520d(F588)VARIOUS DEPT PROJECTS$34,094
30February 10, 2025January 21, 202520d(F588)VARIOUS DEPT PROJECTS$18,110
31February 14, 2025January 23, 202522d(F588)VARIOUS DEPT PROJECTS$31,608
32February 14, 2025January 23, 202522d(F588)VARIOUS DEPT PROJECTS$17,993
33February 14, 2025January 23, 202522d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$16,720
34February 14, 2025January 23, 202522d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$8,000
35February 14, 2025January 23, 202522d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,728
36February 14, 2025January 23, 202522d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$6,907
37March 18, 2025February 25, 202521d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$9,274
38March 18, 2025February 25, 202521d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$8,646
39March 20, 2025February 26, 202522d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$20,240
40March 21, 2025February 25, 202524d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$12,500
41March 24, 2025January 21, 202562d(F588)VARIOUS DEPT PROJECTS$34,094
42March 24, 2025January 21, 202562d(F588)VARIOUS DEPT PROJECTS$18,110
43March 25, 2025February 27, 202526d(F588)VARIOUS DEPT PROJECTS$30,950
44March 25, 2025February 27, 202526d(F588)VARIOUS DEPT PROJECTS$24,284
45April 14, 2025March 19, 202526d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,728
46April 14, 2025March 19, 202526d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,342
47April 14, 2025March 19, 202526d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$6,000
48April 15, 2025March 20, 202526d(F588)VARIOUS DEPT PROJECTS$27,946
49April 15, 2025March 20, 202526d(F588)VARIOUS DEPT PROJECTS$18,346
50April 15, 2025March 20, 202526d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$16,720
51April 16, 2025April 10, 20256d(F588)VARIOUS DEPT PROJECTS$33,272
52April 16, 2025April 10, 20256d(F588)VARIOUS DEPT PROJECTS$19,992
53April 16, 2025April 10, 20256d(F588)USER EXPERIENCE & INTERFACE DESIGNING- RAMONA DSOUZA$17,600
54April 16, 2025April 10, 20256d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$13,000
55April 16, 2025April 10, 20256d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,728
56April 16, 2025April 10, 20256d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$6,665
57May 22, 2025May 6, 202516d(F588)VARIOUS DEPT PROJECTS$31,608
58May 22, 2025May 6, 202516d(F588)VARIOUS DEPT PROJECTS$18,287
59June 3, 2025May 6, 202528d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$16,720
60June 3, 2025May 6, 202528d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$9,000
61June 3, 2025May 6, 202528d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,342
62June 3, 2025May 6, 202528d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$6,859
63June 17, 2025June 13, 20254d(F588)VARIOUS DEPT PROJECTS$39,926
64June 17, 2025June 13, 20254d(F588)VARIOUS DEPT PROJECTS$22,579
65June 17, 2025June 13, 20254d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$21,120
66June 17, 2025June 13, 20254d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$13,500
67June 17, 2025June 13, 20254d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$9,467
68June 17, 2025June 13, 20254d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$9,322
69August 6, 2025July 10, 202527d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$8,163
70August 6, 2025July 10, 202527d(F588)GIS DATABASE MAINTENANCE-EVAN BAGHERI & NIA BEAZER$7,728
71August 7, 2025July 10, 202528d(F588)GIS PORTAL UPGRADES-LAKSHMI BATTINA$10,250
72August 12, 2025July 15, 202528d(F588)VARIOUS DEPT PROJECTS$33,272
73August 12, 2025July 15, 202528d(F588)VARIOUS DEPT PROJECTS$18,816
74August 12, 2025July 15, 202528d(F588) USER EXPERIENCE & INTERFACE DESIGNING-RAMONA DSOUZA$18,480

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.