What has the City paid on purchase order SC54CO20135021K?

$7.83M paid to Ford E C Inc across 18 payments from March 5, 2020 to October 20, 2020, charged to Non-Departmental / Bridge Housing - Beacon St..

What it was for

Bridge Housing - Beacon St.

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1March 5, 2020February 13, 202021d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$234,422
2March 5, 2020February 13, 202021d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$138,557
3March 12, 2020February 28, 202013d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$840,850
4March 12, 2020February 28, 202013d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$400,928
5April 9, 2020March 26, 202014d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$1,459,754
6April 9, 2020March 26, 202014d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$1,157,440
7May 4, 2020April 7, 202027d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$308,750
8May 4, 2020April 7, 202027d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$308,750
9May 7, 2020April 29, 20208d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$776,131
10May 7, 2020April 29, 20208d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$674,945
11June 18, 2020June 4, 202014d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$374,535
12June 18, 2020June 4, 202014d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$290,678
13July 29, 2020July 20, 20209d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$182,001
14July 29, 2020July 20, 20209d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$174,459
15August 19, 2020July 30, 202020d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$273,031
16August 19, 2020July 30, 202020d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$130,072
17October 20, 2020July 30, 202082d100/54/00R678; WORK ORDER# E1908430 - BEACON BH$73,516
18October 20, 2020July 30, 202082d100/54/00S704; WORK ORDER# E1908454 - EUBANK BH$29,341

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.