What has the City paid on purchase order SC54CO19003644K?

$17.22M paid to Ohl USA Inc across 25 payments from March 11, 2019 to March 2, 2021, charged to Non-Departmental / Potrero Canyon Stabiliz & Park.

What it was for

Potrero Canyon Stabiliz & Park

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1March 11, 2019February 12, 201927d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$247,752
2April 18, 2019March 11, 201938d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$283,116
3April 18, 2019December 18, 2018121d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$231,696
4April 18, 2019March 22, 201927d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$163,139
5May 8, 2019April 18, 201920d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,622,655
6June 10, 2019May 15, 201926d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,738,685
7June 24, 2019June 14, 201910d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$409,336
8August 15, 2019August 2, 201913d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,268,440
9August 30, 2019August 16, 201914d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,060,610
10December 16, 2019November 22, 201924d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,616,555
11December 16, 2019November 22, 201924d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,197,255
12January 8, 2020December 9, 201930d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,074,333
13January 8, 2020December 12, 201927d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$816,765
14January 8, 2020December 12, 201927d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$9,284
15February 19, 2020January 30, 202020d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$511,389
16March 25, 2020February 24, 202030d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$667,094
17May 7, 2020March 20, 202048d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$872,811
18May 7, 2020April 17, 202020d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$445,245
19May 7, 2020March 20, 202048dRE-ENCUMBER RETURNED PAYMENT FROM PR1.$231,696
20June 10, 2020June 1, 20209d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$685,370
21July 20, 2020July 9, 202011d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$21,429
22July 28, 2020July 16, 202012d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$1,015,006
23September 23, 2020September 2, 202021d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$85,714
24March 1, 2021February 9, 202120d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$86,069
25March 2, 2021February 4, 202126d100/54/00G998/E1907428 - POTRERO CANYON PARK-GRADING PROJECT$861,129

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.