What has the City paid on purchase order SC50MSACO17128054K?

$1.18M paid to KDC Inc across 9 payments from July 18, 2017 to July 13, 2021, charged to Non-Departmental / Reseda - Arleta HV Conversion.

What it was for

Reseda - Arleta HV Conversion

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

MICLA 2016 Streetlights Construction Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1July 18, 2017June 22, 201726dKDC INC DBA DYNAELECTRIC-RESEDA-ARLETA STM HIGH VOLTAGE CONVERSION FY 2015-16$887,114
2February 9, 2018February 2, 20187dCO128054-RESEDA-ARLETA STM HV CONV FY15-16 PP#5$17,028
3March 21, 2018March 16, 20185dCO128054-RESEDA-ARLETA STM HV CONV FY15-16 PP#6$42,753
4September 21, 2018August 21, 201831dCO128054-RESEDA-ARLETA STM HV CONV FY15-16 PP#8$54,891
5September 21, 2018August 20, 201832dCO128054-RESEDA-ARLETA STM HV CONV FY15-16 PP#7$15,305
6October 16, 2018October 1, 201815dCO128054 RESEDA-ARLETA STM HV CONV FY15-16 PR#9$11,100
7November 29, 2018October 31, 201829dCO128054 RESEDA-ARLETA STM HV CONV - PR#10$67,048
8May 7, 2021March 3, 202165dCO128054 RESEDA-ARLETA STM HV CONV - PR#11$61,187
9July 13, 2021May 24, 202150dCO128054 RESEDA-ARLETA STM HV CONV - PR#12F$27,219

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.