What has the City paid on purchase order SC50MSACO16123910K?

$1.89M paid to 2 different vendors (the largest, John S Meek Company Inc, received $1.7M) across 28 payments from July 14, 2017 to February 4, 2020, charged to Non-Departmental / Mulholland Drive (13319) Bulkhead.

A blanket order, not one firm's contract

2 different vendors draw against this purchase order, so the $1.9M above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

Mulholland Drive (13319) Bulkhead

Budget line carrying the most money, of 5 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Special Gas Tax St Improv

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Paid to

John S Meek Company Inc$1.7M · 24 payments
Jilk Heavy Construction Inc.$220K · 4 payments

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1July 14, 2017July 7, 20177dQUAIL DRIVE (495) PARTIAL BULKHEAD REPLACEMENT - NTP DATED 11/10/16 WO#E1907909$6,280
2July 17, 2017June 19, 201728dASILOMAR BLVD LANDSLIDE DEWATERING PROJ - NTP DATED 10/14/16 WO#E1907810$265,040
3August 28, 2017August 18, 201710dQUAIL DRIVE (495) PARTIAL BULKHEAD REPLACEMENT - NTP DATED 11/10/16 WO#E1907909$6,946
4September 7, 2017August 28, 201710dASILOMAR BLVD LANDSLIDE DEWATERING PROJ - NTP DATED 10/14/16 WO#E1907810$286,128
5September 28, 2017September 14, 201714dASILOMAR BLVD LANDSLIDE DEWATERING PROJ - NTP DATED 10/14/16 WO#E1907810$48,231
6November 15, 2017October 30, 201716dFOR HARDING ST BRIDGE ROCK SLOPE PROTECTOR - NTP DTD 07/18/17 WO#E6000940$267,129
7November 21, 2017November 10, 201711dINCREASE $8,25 ASILOMAR BLVD LANDSLIDE DEWATERING PROJ - NTP DTD 10/14/16 WO#E1907810$48,868
8November 29, 2017November 16, 201713dFOR HARDING ST BRIDGE ROCK SLOPE PROTECTOR - NTP DTD 07/18/17 WO#E6000940$58,653
9January 26, 2018January 17, 20189dINCREASE $52,318.05 CO'S 2 TO 4 FOR ASILOMAR BLVD LANDSLIDE DEWATERING PROJ WO#E190781$17,705
10April 23, 2018March 21, 201833dF206/50NKGC/WO#E1907777-MULHOLLAND DRIVE (13319)BULKHEAD$280,723
11May 9, 2018April 20, 201819dMULHOLLAND DR(13319) BULKHEAD$62,170
12June 14, 2018June 7, 20187dLECCO LANE (17860) BULKHEAD NTP DATED 03/16/16 WO#E1907787$4,409
13June 15, 2018May 24, 201822dMULHOLLAND DRIVE (13319)BULKHEAD$45,798
14July 20, 2018July 11, 20189dFOR HARDING ST BRIDGE ROCK SLOPE PROTECTOR - NTP DTD 07/18/17 WO#E6000940$23,258
15July 30, 2018July 3, 201827dF206/50NKGC/WO#E1907777-MULHOLLAND DRIVE (13319)BULKHEAD$38,789
16August 24, 2018August 9, 201815dINCREASE $52,318.05 CO'S 2 TO 4 FOR ASILOMAR BLVD LANDSLIDE DEWATERING PROJ WO#E190781$33,999
17August 29, 2018August 23, 20186dF206/50NKGC/WO#E1907777-MULHOLLAND DRIVE (13319)BULKHEAD$57,019
18October 9, 2018September 18, 201821dDECREASE BY $29,321.75 CO#6 FOR ASILOMAR BL LANDSLIDE DEWATERING PROJ-NTP DTD 10/14/16 WO#E1907810$18,555
19October 9, 2018September 18, 201821dINCREASE $52,318.05 CO'S 2 TO 4 FOR ASILOMAR BLVD LANDSLIDE DEWATERING PROJ WO#E190781$615
20October 26, 2018October 18, 20188dPP#4 - C123910 WO#E6000940-HARDING ST - RELEASE OF RETENTION$17,844
21November 9, 2018October 24, 201816dC123910 PP#6 - WO#E1907777 MULHOLLAND DR (13319) BULKHEAD$43,139
22June 19, 2019April 29, 201951dPP#5- C123910 WO#E6000940- HARDING ST BRIDGE-ROCK SLOPE PROTECTION$7,875
23August 27, 2019August 22, 20195d206/50NKGC/ E1907777 -MULHOLLAND DR (13319) BULKHEAD$26,253
24August 27, 2019August 22, 20195d206/50NKGC/ E1907777-ADDL ENC-CO#1&3-$31162.70 -MULHOLLAND DR (13319) BULKHEAD$43
25November 19, 2019November 13, 20196dHARDING ST BRIDGE ROCK SLOPE PROTECTOR/WO#E6000940/CHANGE ORDER#1$28,492
26February 4, 2020January 30, 20205d206/50NKGC/WO#E1907777/CO#4, 7, 9 & 10$120,766
27February 4, 2020January 29, 20206d206/50NKGC/ E1907777 -MULHOLLAND DR (13319) BULKHEAD$39,805
28February 4, 2020January 30, 20205d206/50NKGC/ E1907777-ADDL ENC-CO#1&3-$31162.70 -MULHOLLAND DR (13319) BULKHEAD$31,119

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.